Skip to main content
← Back

Tejelevia Building C, Baner

by Tejraj Realtors LLP. Baner, Pune 411045. View on Google Maps

Launched
5 years 8 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
82%Mid-construction
Units booked
108 of 11693% booked
Price per sq ft (incl. balconies and terrace)
₹13,0002024 · 10 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK6
2 BHK52
3 BHK6
4 BHK52
Total units116
Buildings1
Land2.8 acres
Landowner share6
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 104 → 108 · structure 72% → 82%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹13,000 per sq ft10 sales

Rate vs other Baner projects, 2024: about 10% higher

Compared with 6 similar projects in PIN 411045

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 8 mths4 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)December 2028May 2028
Concrete structure (RCC) complete82%100%
Share of units booked93%86%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 5 years 8 months have passed
Concrete structure (RCC) 82% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 10%Jun 2025: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 82%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 82%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%82%0%108
100%72%0%104
100%10%0%96
100%0%0%64
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Tejelevia Building C (MahaRERA P52100050379) is a residential project by Tejraj Realtors LLP in Baner, Pune 411045. It was launched in April 2023. It has 116 units in 1 building, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 82% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

108 of its 116 units are booked (93%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 72% to 82%. 80% of the 2024 sales we found here were at ₹13,000 per sq ft or less, counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate about 10% higher than at other Baner projects in 2024.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050379.Check it on MahaRERA (P52100050379)All projects in Baner, Balewadi, Mahalunge