Skip to main content
← Back

5 Maidan by Skyi, Baner

by Enerrgia Skyi Ventures. Baner, Pune 411045. View on Google Maps

Launched
5 years 1 month promised
Possession date (MahaRERA)
1 year 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possession
Units booked
173 of 19191% booked

Project facts

3 BHK5
4 BHK147
Other units (shops, offices or not given by type)39
Total units191
Buildings1
Land1.1 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 148 → 173 · structure 3% → 100% · final finishes 0% → 65% · complaints 0 → 2

Share on WhatsApp

Compared with 6 similar projects in PIN 411045

Projects with 70–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 1 mth5 yrs 1 mth
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2028July 2028
Concrete structure (RCC) complete100%66%
Share of units booked91%92%
Complaints on MahaRERA (filed by or against the builder)21

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 5 months of the promised 5 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 3%Jun 2025: Concrete structure (RCC) 3%Dec 2025: Concrete structure (RCC) 3%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%65%173
100%3%0%148
100%0%0%146
100%0%0%90

"—" means MahaRERA shows no figure for that update.

About this project

5 Maidan by Skyi (MahaRERA P52100050885) is a residential project by Enerrgia Skyi Ventures in Baner, Pune 411045. It was launched in May 2023. It has 191 units in 1 building: 152 homes (3 & 4 BHK) and 39 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 65% complete. MahaRERA records do not show it as ready to move in.

173 of its 191 units are booked (91%). Since the December 2025 update, 25 more units have been booked and the reported concrete structure (RCC) has gone from 3% to 100%.

Skyi's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date17
Completed after an extension, or lapsed7
Under construction17
Possession date extended by the builder7
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Skyi projects52 (20 of 41 projects)

See all Skyi projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050885.Check it on MahaRERA (P52100050885)All projects in Baner, Balewadi, Mahalunge