Rohan Abhilasha 3, Wagholi

by Rohan Housing Pvt Ltd. Wagholi, Pune 412207. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
5 months awayPossession date unchanged since launch
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
239 of 27986% booked
Price per sq ft (incl. balconies and terrace)
₹8,4002025 · 19 salesup 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK73
2 BHK198
3 BHK8
Total units279
Buildings3
Land3.1 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 235 → 239 · final finishes 13% → 80%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
680 – 870 sq ft₹62 – 68 lakh

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,200 per sq ft119 sales
2025up 2% on 2024₹8,400 per sq ft19 sales

Rate vs other Wagholi projects, 2025: about 35% lower

Studios (under 450 sq ft)

80% of the 2024 studio sales we found were at this rate or less

2024₹8,400 per sq ft12 sales

Sizes 430 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 5 similar projects in PIN 412207

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 11 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)March 2027May 2027
Concrete structure (RCC) complete100%100%
Share of units booked86%66%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 6 months of the promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 67%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 27%Dec 2024: Concrete structure (RCC) 73%Jun 2025: Concrete structure (RCC) 73%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 13%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%239
100%100%13%235
100%73%0%223
100%27%0%129
67%0%0%83

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Rohan Abhilasha 3 (MahaRERA P52100050453) is a residential project by Rohan Housing Pvt Ltd in Wagholi, Pune 412207. It was launched in April 2023. It has 279 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 80% complete. MahaRERA records do not show it as ready to move in.

239 of its 279 units are booked (86%). Since the December 2025 update, 4 more units have been booked. 80% of the 2025 sales we found here were at ₹8,400 per sq ft or less (up 2% on 2024), counting balconies and terrace in the size, based on 19 registered sales. Buyers here paid a rate about 35% lower than at other Wagholi projects in 2025. Most buyers paid ₹62–68 lakh for flats of 680–870 sq ft. Its studios (under 450 sq ft) sold at ₹8,400 per sq ft or less in 2024 (12 sales); studios are priced separately from flats.

Rohan's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA32
Completed without extending the possession date16
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 8 months
Complaints on MahaRERA, all Rohan projects17 (11 of 32 projects)

See all Rohan projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050453.Check it on MahaRERA (P52100050453)All projects in Wagholi