24K Altura, Baner

by Kolte-Patil Developers Limited. Baner, Pune 411045. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Mar 2028 – Dec 2030varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
20%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
Units booked
465 of 52089% booked
Price per sq ft
₹16,1002026 salesup 7% on 2025See what buyers paid

Project facts

3 BHK385
4 BHK133
Total units520
Buildings4
Land0.7 acres
Phases3

Since Dec 2025: booked 117 → 130

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,330 sq ft₹1.89 – 2.21 crore2025 sales
4 BHKabout 1,730 – 1,970 sq ft₹2.59 – 2.98 crore2026 sales

Price per sq ft, year by year

2023₹12,600 per sq ft
2024up 6% on 2023₹13,400 per sq ft
2025up 12% on 2024₹15,000 per sq ft
2026up 7% on 2025₹16,100 per sq ft

Registered sales across all 3 phases.

Compared with the typical Baner rate in 2026: about 15% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
24K Altura - Tower A and B
Mid-construction
P521000513162647%96%
24K Altura - Tower D
Mid-construction
P5210005417515552%84%
24K Altura - Tower C
Mid-construction
P52100077098996%80%
Show updates by phase

24K Altura - Tower A and B (P52100051316)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%254
100%7%0%—
100%0%0%—
50%0%0%—

"—" means MahaRERA shows no figure for that update.

24K Altura - Tower D (P52100054175)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%52%0%130
100%23%0%117
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

24K Altura - Tower C (P52100077098)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%6%0%81
100%6%0%—
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411045

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2028 – Dec 2030January 2028
Concrete structure (RCC)20%48%
Units booked89%73%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

24K Altura is a project by Kolte-Patil Developers Limited in Baner, Pune 411045, registered with MahaRERA as 3 phases (P52100051316, P52100054175, P52100077098). The first phase was launched in June 2023. Together the phases have 520 units in 4 buildings, with 3 & 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from March 2028 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 20% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.

465 of the 520 units reported for sale are booked (89%). In 2026 registered sales, 80% of flats here sold at ₹16,100 per sq ft or less (up 7% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% higher than the typical Baner rate in 2026. Most buyers paid ₹1.89–2.21 crore for 3 BHK flats of about 1,330 sq ft (2025 sales); ₹2.59–2.98 crore for 4 BHK flats of about 1,730–1,970 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension2
Lapsed15
Under construction35
Possession date extended on the builder's application4
Typical time from launch to 100% structure3 years
MahaRERA complaints (filed by or against the builder), all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Source: MahaRERA registrations P52100051316, P52100054175 and P52100077098.Open MahaRERA and search P52100051316All projects in Baner, Balewadi, Mahalunge