24K Altura, Baner
by Kolte-Patil Developers Limited. Baner, Pune 411045. View on Google Maps
- Launched
- First of 3 phases
- Possession dates (MahaRERA)
- Mar 2028 – Dec 2030varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 20%Mid-construction0 of 3 phases with structure completeWeighted across 3 phases
- Units booked
- 465 of 52089% booked
- Price per sq ft
- ₹16,1002026 salesup 7% on 2025See what buyers paid
Facts
Project facts
| 3 BHK | 385 |
|---|---|
| 4 BHK | 133 |
| Total units | 520 |
| Buildings | 4 |
| Land | 0.7 acres |
| Phases | 3 |
Since Dec 2025: booked 117 → 130
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 3 BHK | about 1,330 sq ft | ₹1.89 – 2.21 crore | 2025 sales |
| 4 BHK | about 1,730 – 1,970 sq ft | ₹2.59 – 2.98 crore | 2026 sales |
Price per sq ft, year by year
| 2023 | ₹12,600 per sq ft |
|---|---|
| 2024up 6% on 2023 | ₹13,400 per sq ft |
| 2025up 12% on 2024 | ₹15,000 per sq ft |
| 2026up 7% on 2025 | ₹16,100 per sq ft |
Registered sales across all 3 phases.
Compared with the typical Baner rate in 2026: about 15% higher
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| 24K Altura - Tower A and B Mid-construction | P52100051316 | 264 | 7% | 96% | |
| 24K Altura - Tower D Mid-construction | P52100054175 | 155 | 52% | 84% | |
| 24K Altura - Tower C Mid-construction | P52100077098 | 99 | 6% | 80% |
Show updates by phase
24K Altura - Tower A and B (P52100051316)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 7% | 0% | 254 | |
| 100% | 7% | 0% | — | |
| 100% | 0% | 0% | — | |
| 50% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
24K Altura - Tower D (P52100054175)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 52% | 0% | 130 | |
| 100% | 23% | 0% | 117 | |
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
24K Altura - Tower C (P52100077098)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 6% | 0% | 81 | |
| 100% | 6% | 0% | — | |
| 100% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 411045
Projects with 250–1,100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 2 mths | 4 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Mar 2028 – Dec 2030 | January 2028 |
| Concrete structure (RCC) | 20% | 48% |
| Units booked | 89% | 73% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Palladio Balewadi Central | June 2023 | Dec 2027 – Dec 2028 | 62% | 680 of 730 booked (93%) |
| Godrej Hillside 3 | May 2023 | February 2028 | 45% | 475 of 493 booked (96%) |
| Rohan Ekam | August 2023 | Dec 2027 – Mar 2030 | 51% | 306 of 514 booked (60%) |
| Godrej River Royale | October 2023 | March 2029 | 12% | 125 of 370 booked (34%) |
| Merlin Ventana | November 2023 | December 2028 | 1% | 186 of 255 booked (73%) |
| Kumar Parth | December 2022 | Dec 2027 – May 2030 | 70% | 411 of 558 booked (74%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
24K Altura is a project by Kolte-Patil Developers Limited in Baner, Pune 411045, registered with MahaRERA as 3 phases (P52100051316, P52100054175, P52100077098). The first phase was launched in June 2023. Together the phases have 520 units in 4 buildings, with 3 & 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from March 2028 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 20% complete and final finishes 0% complete. 0 of the 3 phases have their structure complete.
465 of the 520 units reported for sale are booked (89%). In 2026 registered sales, 80% of flats here sold at ₹16,100 per sq ft or less (up 7% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 15% higher than the typical Baner rate in 2026. Most buyers paid ₹1.89–2.21 crore for 3 BHK flats of about 1,330 sq ft (2025 sales); ₹2.59–2.98 crore for 4 BHK flats of about 1,730–1,970 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
Kolte Patil's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 63 |
|---|---|
| Completed without extending the possession date | 11 |
| Completed after an extension | 2 |
| Lapsed | 15 |
| Under construction | 35 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 3 years |
| MahaRERA complaints (filed by or against the builder), all Kolte Patil projects | 100 (28 of 63 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.