Godrej River Royale, Mahalunge

by Mahalunge Township Developers Private Limited. Mahalunge, Pune 411045. View on Google Maps

Launched
5 years 5 months promised
Possession date (MahaRERA)
2 years 5 months awayPossession date unchanged since launch
Concrete structure (RCC)
12%Mid-constructionAverage across 3 buildings
Units booked
125 of 37034% booked
Price per sq ft (incl. balconies and terrace)
₹14,1002026 so far · 22 salesup 6% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

3 BHK288
4 BHK72
Other units (shops, offices or not given by type)10
Total units370
Buildings3
Land4.4 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 115 → 125 · structure 0% → 12%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,690 sq ft₹2.18 – 2.42 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹13,500 per sq ft52 sales
2025down 1% on 2024₹13,300 per sq ft37 sales
2026 so farup 6% on 2025₹14,100 per sq ft22 sales

Rate vs other Mahalunge projects, 2026: about 20% higher

Compared with 6 similar projects in PIN 411045

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 5 mths4 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)March 2029May 2028
Concrete structure (RCC) complete12%52%
Share of units booked34%70%
Complaints on MahaRERA (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years of the promised 5 years 5 months have passed
Concrete structure (RCC) 12% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 12%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 12%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%12%0%125
100%0%0%115
100%0%0%79
100%0%0%160
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Godrej River Royale (MahaRERA P52100052957) is a residential project by Mahalunge Township Developers Private Limited in Mahalunge, Pune 411045. It was launched in October 2023. It has 370 units in 3 buildings: 360 homes (3 & 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2029, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 12% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

125 of its 370 units are booked (34%). Since the December 2025 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 12%. 80% of the 2026 (so far) sales we found here were at ₹14,100 per sq ft or less (up 6% on 2025), counting balconies and terrace in the size, based on 22 registered sales. Buyers here paid a rate about 20% higher than at other Mahalunge projects in 2026. Most buyers paid ₹2.18–2.42 crore for flats of 1,690 sq ft.

Godrej's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA41
Completed without extending the possession date9
Completed after an extension, or lapsed2
Under construction30
Possession date extended by the builder11
Typical time from launch to 100% structure3 years 4 months
Complaints on MahaRERA, all Godrej projects441 (35 of 41 projects)

See all Godrej projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052957.Check it on MahaRERA (P52100052957)All projects in Baner, Balewadi, Mahalunge