Akshara Serenity B and C, Tathawade
Finishing stage
Final finishes 100% · completion not yet filed on MahaRERA
by Garve Developers and Promoters. Tathawade, Pune 411057. View on Google Maps
- Launched
- 2 years 11 months originally promised
- Possession date (MahaRERA)
- 2 months awayExtended by 7 months (originally May 2026). Why possession dates change
- Concrete structure (RCC)
- 100%Finishing stageAverage across 2 buildings
- Units booked
- 32 of 5262% booked
- Price per sq ft (incl. balconies and terrace)
- ₹7,2002024 · 32 sales80% of the 2024 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 52 |
|---|---|
| Total units | 52 |
| Buildings | 2 |
| Land | 0.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 85% → 100% · final finishes 50% → 100% · possession date May 2026 → December 2026
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 760 – 780 sq ft | ₹53 – 56 lakh |
Based on flats sold in 2024.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹7,200 per sq ft | 32 sales |
|---|
Rate vs other Tathawade projects, 2024: about 15% lower
Compared with 6 similar projects in PIN 411057
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 11 mths | 2 yrs 10 mths |
| Possession date extended | By 7 months | 2 of 6 |
| Possession date (MahaRERA) | December 2026 | December 2026 |
| Concrete structure (RCC) complete | 100% | 100% |
| Share of units booked | 62% | 61% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Prithvi Paradise | June 2023 | June 2026 | 100% | 95 of 142 booked (67%) |
| Aditya Enclave | April 2023 | March 2027 | 90% | 22 of 128 booked (17%) |
| A R Atlas | April 2023 | December 2025 | 100% | 62 of 88 booked (70%) |
| Shiv Malhar | August 2023 | December 2026 | 100% | 44 of 122 booked (36%) |
| Trinity Grace | September 2023 | December 2025 | 100% | 43 of 50 booked (86%) |
| Infinia | September 2023 | December 2026 | 75% | 40 of 73 booked (55%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 32 | |
| 90% | 85% | 50% | 32 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Akshara Serenity B and C (MahaRERA P52100051358) is a residential project by Garve Developers and Promoters in Tathawade, Pune 411057. It was launched in June 2023. It has 52 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 7 months from the original May 2026. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.
32 of its 52 units are booked (62%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 85% to 100% and the possession date has moved from May 2026 to December 2026. 80% of the 2024 sales we found here were at ₹7,200 per sq ft or less, counting balconies and terrace in the size, based on 32 registered sales. Buyers here paid a rate about 15% lower than at other Tathawade projects in 2024. Most buyers paid ₹53–56 lakh for flats of 760–780 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.