Geras Island of Joy Project B, Wagholi

by Gera Developments Private Limited. Wagholi, Pune 412207. View on Google Maps

Launched
4 years 9 months promised
Possession date (MahaRERA)
1 year 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
33%Mid-constructionAverage across 3 buildings
Units booked
583 of 62693% booked
Price per sq ft (incl. balconies and terrace)
₹13,1002026 so far · 36 salesup 8% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK10
2 BHK277
3 BHK277
4 BHK62
Total units626
Buildings3
Land3.5 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 542 → 583 · structure 1% → 33% · complaints 1 → 2

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
670 – 680 sq ft₹80 – 85 lakh
870 – 980 sq ft₹1.17 – 1.22 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,600 per sq ft276 sales
2025up 4% on 2024₹12,100 per sq ft96 sales
2026 so farup 8% on 2025₹13,100 per sq ft36 sales

Rate vs other Wagholi projects, 2026: about 10% higher

Compared with 3 similar projects in PIN 412207

Projects with 300–1,300 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 412207
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 9 mths3 yrs 11 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)June 2028August 2027
Concrete structure (RCC) complete33%50%
Share of units booked93%95%
Complaints on MahaRERA (filed by or against the builder)28

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 1 month of the promised 4 years 9 months have passed
Concrete structure (RCC) 33% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 95%Dec 2024: Excavation 98%Jun 2025: Excavation 98%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 1%Jul 2026: Concrete structure (RCC) 33%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 33%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%583
100%1%0%542
98%0%0%455
95%0%0%386
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Geras Island of Joy Project B (MahaRERA P52100052474) is a residential project by Gera Developments Private Limited in Wagholi, Pune 412207. It was launched in September 2023. It has 626 units in 3 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 33% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

583 of its 626 units are booked (93%). Since the December 2025 update, 41 more units have been booked and the reported concrete structure (RCC) has gone from 1% to 33%. 80% of the 2026 (so far) sales we found here were at ₹13,100 per sq ft or less (up 8% on 2025), counting balconies and terrace in the size, based on 36 registered sales. Buyers here paid a rate about 10% higher than at other Wagholi projects in 2026. Most buyers paid ₹80–85 lakh for flats of 670–680 sq ft and ₹1.17–1.22 crore for 870–980 sq ft.

Gera's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA17
Completed without extending the possession date1
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder2
Typical time from launch to 100% structure4 years 1 month
Complaints on MahaRERA, all Gera projects78 (11 of 17 projects)

See all Gera projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100052474.Check it on MahaRERA (P52100052474)All projects in Wagholi