Sky World, Wakad
by Siyaram Developers. Wakad, Pune 411057. View on Google Maps
- Launched
- 3 years 1 month promised
- Possession date (MahaRERA)
- This monthPossession date unchanged since launch
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 2 buildings
- Units booked
- 45 of 11539% booked
- Price per sq ft (incl. balconies and terrace)
- ₹10,7002026 so far · 18 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 RK | 2 |
|---|---|
| 2 BHK | 56 |
| 3 BHK | 56 |
| 5+ BHK | 1 |
| Total units | 115 |
| Buildings | 2 |
| Land | 1.6 acres |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 40 → 45 · structure 95% → 100% · final finishes 20% → 28%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 1,060 – 1,070 sq ft | ₹95 lakh – ₹1.13 crore |
Based on flats sold in 2025.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹10,000 per sq ft | 28 sales |
|---|---|---|
| 2025up 7% on 2024 | ₹10,700 per sq ft | 21 sales |
| 2026 so farabout the same as 2025 | ₹10,700 per sq ft | 18 sales |
Rate vs other Wakad projects, 2026: about 5% lower
Compared with 6 similar projects in PIN 411057
Projects with 50–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 1 mth | 3 yrs 10 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | October 2026 | July 2027 |
| Concrete structure (RCC) complete | 100% | 92% |
| Share of units booked | 39% | 58% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ashiana Malhar Phase II | September 2023 | May 2027 | 100% | 210 of 220 booked (95%) |
| Shiv Malhar | August 2023 | December 2026 | 100% | 44 of 122 booked (36%) |
| Siddhi Nisarg C Building | October 2023 | December 2026 | 100% | 92 of 95 booked (97%) |
| Zenone B Building | October 2023 | September 2027 | 65% | 4 of 94 booked (4%) |
| Param | October 2023 | December 2027 | 85% | 107 of 175 booked (61%) |
| Hinjewadi Premium-Tower 7 | December 2023 | December 2028 | 75% | 79 of 140 booked (56%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 28% | 45 | |
| 100% | 95% | 20% | 40 | |
| 100% | 90% | 0% | 30 | |
| 100% | 53% | 0% | 12 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Sky World (MahaRERA P52100052484) is a residential project by Siyaram Developers in Wakad, Pune 411057. It was launched in September 2023. It has 115 units in 2 buildings, with 1 RK, 2 BHK, 3 BHK & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is October 2026, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) complete, final finishes 28% complete. MahaRERA records do not show it as ready to move in.
45 of its 115 units are booked (39%). Since the December 2025 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 95% to 100%. 80% of the 2026 (so far) sales we found here were at ₹10,700 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 18 registered sales. Buyers here paid a rate about 5% lower than at other Wakad projects in 2026. Most buyers paid ₹95 lakh–₹1.13 crore for flats of 1,060–1,070 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.