Stella, Dudulgaon

by DMK Infrastructure PVT Ltd. Dudulgaon, Pune 412105. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Nov 2026 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
43%Mid-construction2 of 4 phases with structure completeWeighted across 4 phases
Units booked
133 of 15884% booked · 2 phases not reported

Project facts

1 RK2
2 BHK330
3 BHK54
Total units392
Buildings4
Land8 acres
Phases4

Since Dec 2025: booked 51 → 133

Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Stella B1
Nearing possession
P52100053511110100%85%
Stella F1
Nearing possession
P5210005456756100%61%
Stella B3
Early stage
PR12600026008521090%Not reported
Stella A
Early stage
PR12600026009371090%Not reported
Show updates by phase

Stella B1 (P52100053511)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%95
0%0%0%13
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Stella F1 (P52100054567)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%38
0%0%0%38
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Stella B3 (PR1260002600852)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Stella A (PR1260002600937)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 412105

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 412105
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs4 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)Nov 2026 – Dec 2029December 2027
Concrete structure (RCC)43%84%
Units booked84%92%
MahaRERA complaints (filed by or against the builder)20

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

Other phases of this project

About this project

Stella is a project by DMK Infrastructure PVT Ltd in Dudulgaon, Pune 412105, registered with MahaRERA as 4 phases (P52100053511, P52100054567, PR1260002600852, PR1260002600937). The first phase was launched in November 2023. Together the phases have 392 units in 4 buildings, with 1 RK, 2 BHK & 3 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from November 2026 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 43% complete and final finishes 7% complete. 2 of the 4 phases have their structure complete.

133 of the 158 units reported for sale are booked (84%); 2 phases have not reported bookings.

Source: MahaRERA registrations P52100053511, P52100054567, PR1260002600852 and PR1260002600937.Open MahaRERA and search P52100053511All projects in Charholi, Moshi