Skip to main content
← Back

IOS Prime, Tathawade

by Linux Group. Tathawade, Pune 411033. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
46 of 10444% booked
Price per sq ft (incl. balconies and terrace)
₹9,0002025 · 16 salesup 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK1
2 BHK39
3 BHK64
Total units104
Buildings2
Land3.1 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 31 → 46

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,050 – 1,130 sq ft₹90 lakh – ₹1.02 crore

Based on flats sold in 2025.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹8,800 per sq ft25 sales
2025up 2% on 2024₹9,000 per sq ft16 sales

Rate vs other Tathawade projects, 2025: similar

Compared with 6 similar projects in PIN 411033

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs3 yrs 10 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)December 2028November 2027
Concrete structure (RCC) complete0%82%
Share of units booked44%63%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 10 months of the promised 5 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 73%Jun 2025: Excavation 73%Dec 2025: Excavation 85%Jul 2026: Excavation 85%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 85%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
85%0%0%46
85%0%0%31
73%0%0%24
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

IOS Prime (MahaRERA P52100053819) is a residential project by Linux Group in Tathawade, Pune 411033. It was launched in December 2023. It has 104 units in 2 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation 85% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

46 of its 104 units are booked (44%). Since the December 2025 update, 15 more units have been booked. 80% of the 2025 sales we found here were at ₹9,000 per sq ft or less (up 2% on 2024), counting balconies and terrace in the size, based on 16 registered sales. Buyers here paid a rate similar to other Tathawade projects in 2025. Most buyers paid ₹90 lakh–₹1.02 crore for flats of 1,050–1,130 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100053819.Check it on MahaRERA (P52100053819)All projects in Tathawade, Punawale, Jambhe