IOS Prime B1, Tathawade
by Linux Group. Tathawade, Pune 411033. View on Google Maps
- Launched
- 4 years 10 months promised
- Possession date (MahaRERA)
- 3 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 0%Early stage
- Units booked
- 52 of 13439% booked
- Price per sq ft (incl. balconies and terrace)
- ₹9,6002026 so far · 13 salesup 8% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 65 |
|---|---|
| 3 BHK | 67 |
| 4 BHK | 2 |
| Total units | 134 |
| Buildings | 1 |
| Land | 3.1 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 30 → 52 · total units 71 → 134
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 750 – 760 sq ft | ₹63 – 67 lakh |
Based on flats sold in 2025.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹8,900 per sq ft | 54 sales |
|---|---|---|
| 2026 so farup 8% on 2025 | ₹9,600 per sq ft | 13 sales |
Rate vs other Tathawade projects, 2026: about 5% lower
Compared with 6 similar projects in PIN 411033
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 10 mths | 3 yrs 3 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | December 2029 | December 2028 |
| Concrete structure (RCC) complete | 0% | 25% |
| Share of units booked | 39% | 35% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Panoreeva Greens | January 2025 | December 2028 | 0% | 24 of 144 booked (17%) |
| Anika Piccadilly Phase 3 | January 2025 | December 2028 | 90% | 56 of 164 booked (34%) |
| 41 Zillenia Phase 2 | January 2025 | August 2027 | 70% | 129 of 166 booked (78%) |
| Meridian Square | March 2025 | December 2028 | 50% | 50 of 93 booked (54%) |
| Prayagraj | March 2025 | December 2027 | 0% | Bookings not reported |
| Udyam Nagari | March 2025 | December 2029 | 0% | 21 of 60 booked (35%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 52 | |
| 100% | 0% | 0% | 30 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
IOS Prime B1 (MahaRERA P52100079123) is a residential project by Linux Group in Tathawade, Pune 411033. It was launched in February 2025. It has 134 units in 1 building, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
52 of its 134 units are booked (39%). Since the December 2025 update, 22 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹9,600 per sq ft or less (up 8% on 2025), counting balconies and terrace in the size, based on 13 registered sales. Buyers here paid a rate about 5% lower than at other Tathawade projects in 2026. Most buyers paid ₹63–67 lakh for flats of 750–760 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.