Supreme Towers, Mundhwa

by Eastwood Realty LLP. Mundhwa, Pune 411036. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Jun 2029No phase has an extended possession date
Concrete structure (RCC)
8%Mid-construction0 of 2 phases with structure completeWeighted across 2 phases
Units booked
123 of 23153% booked
Price per sq ft
₹20,8002026 salesup 2% on 2025See what buyers paid

Project facts

2 BHK13
3 BHK116
4 BHK109
Total units246
Buildings2
Land1.2 acres
Phases2

Since Dec 2025: booked 97 → 123

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
4 BHKabout 1,430 – 2,180 sq ft₹2.88 – 4.51 crore2026 sales

Price per sq ft, year by year

2024₹19,100 per sq ft
2025up 6% on 2024₹20,300 per sq ft
2026up 2% on 2025₹20,800 per sq ft

Registered sales across all 2 phases.

Compared with the typical Mundhwa rate in 2026: about 60% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Supreme Towers Phase I
Mid-construction
P5210005386811915%59%
Supreme Towers Phase II
Mid-construction
P521000560951191%41%
Show updates by phase

Supreme Towers Phase I (P52100053868)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%73
100%0%0%70
100%0%0%61
100%0%0%19
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Supreme Towers Phase II (P52100056095)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%1%0%50
100%0%0%27
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 5 similar projects in PIN 411036

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411036
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 4 mths3 yrs 9 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)Jun 2029December 2027
Concrete structure (RCC)8%10%
Units booked53%76%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Supreme Towers is a project by Eastwood Realty LLP in Mundhwa, Pune 411036, registered with MahaRERA as 2 phases (P52100053868, P52100056095). The first phase was launched in December 2023. Together the phases have 246 units in 2 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 8% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

123 of the 231 units reported for sale are booked (53%). In 2026 registered sales, 80% of flats here sold at ₹20,800 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 60% higher than the typical Mundhwa rate in 2026. Most buyers paid ₹2.88–4.51 crore for 4 BHK flats of about 1,430–2,180 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100053868 and P52100056095.Open MahaRERA and search P52100053868All projects in Mundhwa, Keshavnagar