Platinum Marvelle, Balewadi

by Platinum Buildcon Private Limited. Balewadi, Pune 411045. View on Google Maps

Launched
3 years 11 months originally promised
Possession date (MahaRERA)
2 years 2 months awayExtended by 1 year (originally December 2027). Why possession dates change
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
45 of 9348% booked
Price per sq ft (incl. balconies and terrace)
₹11,7002026 so far · 41 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK2
1 BHK12
2 BHK36
3 BHK28
4 BHK12
Other units (shops, offices or not given by type)3
Total units93
Buildings2
Land1.2 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 29 → 45 · possession date December 2027 → December 2028 · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
890 sq ft₹93 lakh – ₹1.06 crore
1,390 sq ft₹1.47 – 1.66 crore
1,720 sq ft₹1.63 – 2.01 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹11,400 per sq ft11 sales
2025up 3% on 2024₹11,700 per sq ft18 sales
2026 so farabout the same as 2025₹11,700 per sq ft41 sales

Rate vs other Balewadi projects, 2026: about 20% lower

Compared with 6 similar projects in PIN 411045

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 8 mths
Possession date extendedBy 1 year0 of 6
Possession date (MahaRERA)December 2028September 2027
Concrete structure (RCC) complete0%66%
Share of units booked48%74%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 9 months of the originally promised 3 years 11 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 0%Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%0%0%45
95%0%0%29
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Platinum Marvelle (MahaRERA P52100054345) is a residential project by Platinum Buildcon Private Limited in Balewadi, Pune 411045. It was launched in January 2024. It has 93 units in 2 buildings: 90 homes (1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 1 year from the original December 2027. Construction, averaged across its 2 buildings: excavation 95% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

45 of its 93 units are booked (48%). Since the December 2025 update, 16 more units have been booked and the possession date has moved from December 2027 to December 2028. 80% of the 2026 (so far) sales we found here were at ₹11,700 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 41 registered sales. Buyers here paid a rate about 20% lower than at other Balewadi projects in 2026. Most buyers paid ₹93 lakh–₹1.06 crore for flats of 890 sq ft, ₹1.47–1.66 crore for 1,390 sq ft and ₹1.63–2.01 crore for 1,720 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054345.Check it on MahaRERA (P52100054345)All projects in Baner, Balewadi, Mahalunge