Skip to main content
← Back

Orizzonte Phase - I, Sus

by Galaxy Ventures. Sus, Pune 411021. View on Google Maps

Launched
3 years 11 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
39%Mid-constructionAverage across 4 buildings
Units booked
282 of 42367% booked
Price per sq ft (incl. balconies and terrace)
₹10,4002026 so far · 127 salesup 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK83
3 BHK256
4 BHK39
5+ BHK2
Other units (shops, offices or not given by type)43
Total units423
Buildings4
Land4.6 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 204 → 282 · structure 20% → 39% · total units 269 → 423

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,080 – 1,130 sq ft₹1.00 – 1.21 crore
1,600 – 1,770 sq ft₹1.45 – 1.89 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,300 per sq ft124 sales
2025down 2% on 2024₹10,100 per sq ft38 sales
2026 so farup 3% on 2025₹10,400 per sq ft127 sales

Rate vs other Sus projects, 2026: about 25% higher

Compared with 4 similar projects in PIN 411021

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths4 yrs 6 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)December 2027December 2028
Concrete structure (RCC) complete39%0%
Share of units booked67%44%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 9 months of the promised 3 years 11 months have passed
Concrete structure (RCC) 39% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 20%Dec 2024: Excavation 50%Jun 2025: Excavation 50%Dec 2025: Excavation 93%Jul 2026: Excavation 98%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 20%Jul 2026: Concrete structure (RCC) 39%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 98%Concrete structure (RCC) 39%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
98%39%0%282
93%20%0%204
50%0%0%137
20%0%0%100

"—" means MahaRERA shows no figure for that update.

About this project

Orizzonte Phase - I (MahaRERA P52100054519) is a residential project by Galaxy Ventures in Sus, Pune 411021. It was launched in January 2024. It has 423 units in 4 buildings: 380 homes (2, 3, 4 & 5+ BHK) and 43 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 4 buildings: excavation 98% complete, structure (RCC) 39% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

282 of its 423 units are booked (67%). Since the December 2025 update, 78 more units have been booked and the reported concrete structure (RCC) has gone from 20% to 39%. 80% of the 2026 (so far) sales we found here were at ₹10,400 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size, based on 127 registered sales. Buyers here paid a rate about 25% higher than at other Sus projects in 2026. Most buyers paid ₹1.00–1.21 crore for flats of 1,080–1,130 sq ft and ₹1.45–1.89 crore for 1,600–1,770 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100054519.Check it on MahaRERA (P52100054519)All projects in Bavdhan, Pashan, Sus