Nyati Equinox II, Bavdhan Khurd
by Mihir Homes Enterprise LLP. Bavdhan Khurd, Pune 411021. View on Google Maps
- Launched
- 3 years 3 months promised
- Possession date (MahaRERA)
- 7 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 66%Mid-constructionAverage across 2 buildings
- Units booked
- 96 of 23840% booked
- Price per sq ft (incl. balconies and terrace)
- ₹9,7002026 so far · 11 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 131 |
|---|---|
| 2 BHK | 52 |
| 3 BHK | 51 |
| Other units (shops, offices or not given by type) | 4 |
| Total units | 238 |
| Buildings | 2 |
| Land | 3.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 86 → 96 · structure 45% → 66% · final finishes 4% → 6%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2026 so far | ₹9,700 per sq ft | 11 sales |
|---|
Rate vs other Bavdhan Khurd projects, 2026: about 15% lower
Compared with 6 similar projects in PIN 411021
Projects with 100–500 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 3 mths | 4 yrs 2 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | May 2027 | March 2028 |
| Concrete structure (RCC) complete | 66% | 24% |
| Share of units booked | 40% | 58% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dream Delmont | February 2024 | March 2029 | 0% | 131 of 275 booked (48%) |
| Unique Sky Links Phase I | March 2024 | June 2027 | 100% | 53 of 117 booked (45%) |
| Orizzonte Phase - I | January 2024 | December 2027 | 39% | 282 of 423 booked (67%) |
| M Soul Strings Wing C | April 2024 | December 2029 | 100% | 117 of 155 booked (75%) |
| Livience Aleenta- Phase II | December 2023 | May 2028 | 3% | 47 of 147 booked (32%) |
| Ganga Legend B5 Building | June 2024 | December 2027 | 8% | 143 of 214 booked (67%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 90% | 66% | 6% | 96 | |
| 90% | 45% | 4% | 86 | |
| 85% | 5% | 0% | — | |
| 80% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Nyati Equinox II (MahaRERA P52100054912) is a residential project by Mihir Homes Enterprise LLP in Bavdhan Khurd, Pune 411021. It was launched in February 2024. It has 238 units in 2 buildings: 234 homes (1, 2 & 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is May 2027, unchanged since launch. Construction, averaged across its 2 buildings: excavation 90% complete, structure (RCC) 66% complete, final finishes 6% complete. MahaRERA records do not show it as ready to move in.
96 of its 238 units are booked (40%). Since the December 2025 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 45% to 66%. 80% of the 2026 (so far) sales we found here were at ₹9,700 per sq ft or less, counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 15% lower than at other Bavdhan Khurd projects in 2026.
Nyati's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 48 |
|---|---|
| Completed without extending the possession date | 24 |
| Completed after an extension, or lapsed | 12 |
| Under construction | 12 |
| Possession date extended by the builder | 6 |
| Typical time from launch to 100% structure | 2 years 1 month |
| Complaints on MahaRERA, all Nyati projects | 32 (14 of 48 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.