Vrindavan Heights Phase III, Hadapsar
by Kwality World Developers (Aop). Hadapsar, Pune 411028. View on Google Maps
- Launched
- 3 years 1 month originally promised
- Possession date (MahaRERA)
- 1 year 5 months awayExtended by 1 year (originally March 2027). Why possession dates change
- Concrete structure (RCC)
- 78%Mid-construction
- Units booked
- 32 of 12027% booked
- Price per sq ft (incl. balconies and terrace)
- ₹10,4002026 so far · 27 salesup 4% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 BHK | 1 |
|---|---|
| 2 BHK | 61 |
| 3 BHK | 57 |
| 5+ BHK | 1 |
| Total units | 120 |
| Buildings | 1 |
| Land | 3.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 16 → 32 · structure 30% → 78%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 880 sq ft | ₹85 – 89 lakh |
| 1,000 – 1,090 sq ft | ₹98 lakh – ₹1.17 crore |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2025 | ₹10,000 per sq ft | 16 sales |
|---|---|---|
| 2026 so farup 4% on 2025 | ₹10,400 per sq ft | 27 sales |
Rate vs other Hadapsar projects, 2026: about 5% lower
Compared with 5 similar projects in PIN 411028
Projects with 60–250 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 1 mth | 4 yrs 6 mths |
| Possession date extended | By 1 year | 0 of 5 |
| Possession date (MahaRERA) | March 2028 | December 2028 |
| Concrete structure (RCC) complete | 78% | 100% |
| Share of units booked | 27% | 81% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Akshar Altorios 2.O | January 2024 | December 2027 | 77% | 57 of 120 booked (48%) |
| Yashraj Nakshatra Phase 2 | March 2024 | December 2027 | 100% | 132 of 157 booked (84%) |
| Silver Astra | June 2024 | December 2028 | 30% | 70 of 144 booked (49%) |
| Kumar Primeview E1 | October 2023 | December 2028 | 100% | 194 of 239 booked (81%) |
| Kumar Primeview E2 | October 2023 | December 2028 | 100% | 197 of 241 booked (82%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 78% | 0% | 32 | |
| 100% | 30% | 0% | 16 | |
| 100% | 0% | 0% | — | |
| 90% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Vrindavan Heights Phase III (MahaRERA P52100054968) is a residential project by Kwality World Developers (Aop) in Hadapsar, Pune 411028. It was launched in February 2024. It has 120 units in 1 building, with 1, 2, 3 & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2028, extended by 1 year from the original March 2027. Construction: excavation complete, structure (RCC) 78% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
32 of its 120 units are booked (27%). Since the December 2025 update, 16 more units have been booked and the reported concrete structure (RCC) has gone from 30% to 78%. 80% of the 2026 (so far) sales we found here were at ₹10,400 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size, based on 27 registered sales. Buyers here paid a rate about 5% lower than at other Hadapsar projects in 2026. Most buyers paid ₹85–89 lakh for flats of 880 sq ft and ₹98 lakh–₹1.17 crore for 1,000–1,090 sq ft.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.