VTP Dolce Vita Phase 3, Manjari Khurd

by Ashdan Developers Private Limited. Manjari Khurd, Pune 412307. View on Google Maps

Launched
5 years 3 months promised
Possession date (MahaRERA)
2 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
38%Mid-constructionAverage across 2 buildings
Units booked
368 of 48476% booked
Price per sq ft (incl. balconies and terrace)
₹11,3002026 so far · 25 salesup 3% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK26
2 BHK384
3 BHK64
Other units (shops, offices or not given by type)10
Total units484
Buildings2
Land1.1 acres
Landowner share9
Complaints on MahaRERA (filed by or against the builder)9

Since Dec 2025: booked 360 → 368 · structure 10% → 38% · complaints 5 → 9

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
850 sq ft₹95 – 97 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,400 per sq ft257 sales
2025up 6% on 2024₹11,000 per sq ft49 sales
2026 so farup 3% on 2025₹11,300 per sq ft25 sales

Rate vs other Manjari Khurd projects, 2026: similar

Compared with 3 similar projects in PIN 412307

Projects with 200–1,000 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 412307
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 3 mths4 yrs 10 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)June 2029May 2028
Concrete structure (RCC) complete38%85%
Share of units booked76%40%
Complaints on MahaRERA (filed by or against the builder)90

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years 7 months of the promised 5 years 3 months have passed
Concrete structure (RCC) 38% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 38%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 38%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%38%0%368
100%10%0%360
100%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

VTP Dolce Vita Phase 3 (MahaRERA P52100055407) is a residential project by Ashdan Developers Private Limited in Manjari Khurd, Pune 412307. It was launched in March 2024. It has 484 units in 2 buildings: 474 homes (1, 2 & 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 38% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

368 of its 484 units are booked (76%). Since the December 2025 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 10% to 38%. 80% of the 2026 (so far) sales we found here were at ₹11,300 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size, based on 25 registered sales. Buyers here paid a rate similar to other Manjari Khurd projects in 2026. Most buyers paid ₹95–97 lakh for flats of 850 sq ft.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100055407.Check it on MahaRERA (P52100055407)All projects in Manjari, Shewalewadi