VTP Dolce Vita Phase 4, Manjari Khurd
by Ashdan Developers Private Limited. Manjari Khurd, Pune 412307. View on Google Maps
- Launched
- 5 years 2 months promised
- Possession date (MahaRERA)
- 2 years 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 44%Mid-construction
- Units booked
- 99 of 20449% booked
- Price per sq ft (incl. balconies and terrace)
- ₹11,4002026 so far · 22 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 64 |
|---|---|
| 3 BHK | 128 |
| Other units (shops, offices or not given by type) | 12 |
| Total units | 204 |
| Buildings | 1 |
| Land | 1.1 acres |
| Landowner share | 12 |
| Complaints on MahaRERA (filed by or against the builder) | 5 |
Since Dec 2025: booked 88 → 99 · structure 11% → 44% · complaints 3 → 5
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Flat sizes and prices
| Flat size | What most buyers paid |
|---|---|
| 860 sq ft | ₹94 – 98 lakh |
Based on flats sold in 2026 so far.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹10,700 per sq ft | 59 sales |
|---|---|---|
| 2026 so far | ₹11,400 per sq ft | 22 sales |
Rate vs other Manjari Khurd projects, 2026: similar
Compared with 5 similar projects in PIN 412307
Projects with 90–400 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 5 yrs 2 mths | 4 yrs 5 mths |
| Possession date extended | No | 1 of 5 |
| Possession date (MahaRERA) | June 2029 | October 2028 |
| Concrete structure (RCC) complete | 44% | 75% |
| Share of units booked | 49% | 61% |
| Complaints on MahaRERA (filed by or against the builder) | 5 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| EAST WORLD Phase - I | February 2024 | December 2028 | 75% | 122 of 184 booked (66%) |
| Godrej River Crest | July 2024 | June 2030 | 0% | 88 of 216 booked (41%) |
| Joyville Celestia Phase 5 | July 2024 | October 2028 | 20% | 103 of 169 booked (61%) |
| Joyville Hadapsar Annexe Phase 17 | January 2024 | December 2027 | 85% | 101 of 252 booked (40%) |
| Joyville Celestia Phase 1 | October 2023 | March 2028 | 85% | 103 of 160 booked (64%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 44% | 0% | 99 | |
| 100% | 11% | 0% | 88 | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
VTP Dolce Vita Phase 4 (MahaRERA P52100055619) is a residential project by Ashdan Developers Private Limited in Manjari Khurd, Pune 412307. It was launched in April 2024. It has 204 units in 1 building: 192 homes (2 & 3 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 44% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
99 of its 204 units are booked (49%). Since the December 2025 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 11% to 44%. 80% of the 2026 (so far) sales we found here were at ₹11,400 per sq ft or less, counting balconies and terrace in the size, based on 22 registered sales. Buyers here paid a rate similar to other Manjari Khurd projects in 2026. Most buyers paid ₹94–98 lakh for flats of 860 sq ft.
VTP's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 70 |
|---|---|
| Completed without extending the possession date | 26 |
| Completed after an extension, or lapsed | 13 |
| Under construction | 31 |
| Possession date extended by the builder | 10 |
| Typical time from launch to 100% structure | 4 years 11 months |
| Complaints on MahaRERA, all VTP projects | 656 (60 of 70 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.