Rudrakshum Residency, Kharadi
by Rudrakshum Constructions Private Limited. Kharadi, Pune 411014. View on Google Maps
- Launched
- 1 year 9 months originally promised
- Possession date (MahaRERA)
- 1 year 5 months awayExtended by 2 years (originally March 2026). Why possession dates change
- Concrete structure (RCC)
- 67%Mid-construction
- Units booked
- 10 of 1953% booked
Project facts
| 1 BHK | 3 |
|---|---|
| 2 BHK | 12 |
| Other units (shops, offices or not given by type) | 4 |
| Total units | 19 |
| Buildings | 1 |
| Land | 0.2 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: possession date March 2026 → March 2028
Compared with 4 similar projects in PIN 411014
Projects with up to 30 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 1 yr 9 mths | 2 yrs 8 mths |
| Possession date extended | By 2 years | 1 of 4 |
| Possession date (MahaRERA) | March 2028 | January 2027 |
| Concrete structure (RCC) complete | 67% | 58% |
| Share of units booked | 53% | 33% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| VJ IndiLife Kharadi | May 2024 | December 2028 | 70% | 813 of 835 booked (97%) |
| Highlife Survey NO 56/3/37/1P , 56/3/26/3 at Wadgaonsheri | May 2024 | December 2026 | 45% | 5 of 34 booked (15%) |
| Samruddhi | August 2024 | December 2026 | 100% | Bookings not reported |
| Vishalleela Residency | April 2024 | March 2027 | 40% | 8 of 24 booked (33%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 67% | 0% | 10 | |
| 100% | 20% | 0% | 7 | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Rudrakshum Residency (MahaRERA P52100066464) is a residential project by Rudrakshum Constructions Private Limited in Kharadi, Pune 411014. It was launched in June 2024. It has 19 units in 1 building: 15 homes (1 & 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2028, extended by 2 years from the original March 2026. Construction: excavation complete, structure (RCC) 67% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
10 of its 19 units are booked (53%). Since the December 2025 update, the possession date has moved from March 2026 to March 2028.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.