VJ IndiLife Kharadi
by Vilas Javdekar Greenscape Developers LLP. Kharadi, Pune 411014. View on Google Maps
- Launched
- 4 years 7 months promised
- Possession date (MahaRERA)
- 2 years 2 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 70%Mid-constructionAverage across 2 buildings
- Units booked
- 813 of 83597% booked
- Price per sq ft (incl. balconies and terrace)
- ₹19,600studios · 2025 · 303 salesup 5% on 202480% of the 2025 studio sales we found were at this rate or lessSee what buyers paid
Project facts
| 1 RK | 762 |
|---|---|
| 1 BHK | 18 |
| Other units (shops, offices or not given by type) | 55 |
| Total units | 835 |
| Buildings | 2 |
| Land | 1.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 800 → 813 · structure 58% → 70%
What buyers paid here
Studios (under 450 sq ft)
₹19,600 per sq ft · studios · 2025 · 303 sales
80% of the 2025 studio sales we found were at this rate or less
| 2024 | ₹18,600 per sq ft | 445 sales |
|---|---|---|
| 2025up 5% on 2024 | ₹19,600 per sq ft | 303 sales |
Sizes 150 – 210 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.
Compared with 6 similar projects in PIN 411014
Projects with up to 40 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 7 mths | 2 yrs 8 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | December 2028 | July 2027 |
| Concrete structure (RCC) complete | 70% | 56% |
| Share of units booked | 97% | 33% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Highlife Survey NO 56/3/37/1P , 56/3/26/3 at Wadgaonsheri | May 2024 | December 2026 | 45% | 5 of 34 booked (15%) |
| Rudrakshum Residency | June 2024 | March 2028 | 67% | 10 of 19 booked (53%) |
| Vishalleela Residency | April 2024 | March 2027 | 40% | 8 of 24 booked (33%) |
| Ayodhyaa Niwaas | April 2024 | December 2027 | 16% | 3 of 38 booked (8%) |
| Samruddhi | August 2024 | December 2026 | 100% | Bookings not reported |
| Kumar Palaash A2 | November 2023 | October 2028 | 100% | All 35 units booked |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 813 | |
| 100% | 58% | 0% | 800 | |
| 98% | 0% | 0% | 493 | |
| 70% | 0% | 0% | 133 |
"—" means MahaRERA shows no figure for that update.
About this project
VJ IndiLife Kharadi (MahaRERA P52100056019) is a residential project by Vilas Javdekar Greenscape Developers LLP in Kharadi, Pune 411014. It was launched in May 2024. It has 835 units in 2 buildings: 780 homes (1 RK & 1 BHK) and 55 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 70% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
813 of its 835 units are booked (97%). Since the December 2025 update, 13 more units have been booked and the reported concrete structure (RCC) has gone from 58% to 70%. Its studios (under 450 sq ft) sold at ₹19,600 per sq ft or less in 2025 (303 sales); studios are priced separately from flats.
Vilas Javdekar's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 45 |
|---|---|
| Completed without extending the possession date | 25 |
| Completed after an extension, or lapsed | 1 |
| Under construction | 19 |
| Possession date extended by the builder | 1 |
| Typical time from launch to 100% structure | 2 years 10 months |
| Complaints on MahaRERA, all Vilas Javdekar projects | 27 (19 of 45 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.