Skip to main content
← Back

Pune Baner Project-Tower 3

by Goel Ganga Ventures India Private Limited. Baner, Pune 411045. View on Google Maps

Launched
4 years 8 months originally promised
Possession date (MahaRERA)
3 years 8 months awayExtended by 1 year (originally June 2029). Why possession dates change
Concrete structure (RCC)
2%Mid-construction
Units booked
80 of 13758% booked

Project facts

3 BHK70
4 BHK61
5+ BHK6
Total units137
Buildings1
Land8.7 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 0% → 2% · possession date June 2029 → June 2030

Share on WhatsApp

Compared with 4 similar projects in PIN 411045

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 8 mths4 yrs 11 mths
Possession date extendedBy 1 year0 of 4
Possession date (MahaRERA)June 2030June 2029
Concrete structure (RCC) complete2%20%
Share of units booked58%53%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
2 years of the originally promised 4 years 8 months have passed
Concrete structure (RCC) 2% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 0%Jun 2025: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 2%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 2%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%2%0%80
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Pune Baner Project-Tower 3 (MahaRERA P52100077575) is a residential project by Goel Ganga Ventures India Private Limited in Baner, Pune 411045. It was launched in October 2024. It has 137 units in 1 building, with 3, 4 & 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2030, extended by 1 year from the original June 2029. Construction: excavation complete, structure (RCC) 2% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

80 of its 137 units are booked (58%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 0% to 2% and the possession date has moved from June 2029 to June 2030.

Goel Ganga's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA61
Completed without extending the possession date18
Completed after an extension, or lapsed14
Under construction29
Possession date extended by the builder16
Typical time from launch to 100% structure5 years 1 month
Complaints on MahaRERA, all Goel Ganga projects141 (27 of 61 projects)

See all Goel Ganga projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100077575.Check it on MahaRERA (P52100077575)All projects in Baner, Balewadi, Mahalunge