Pune Baner Project-Tower 4 and 5
by Goel Ganga Ventures India Private Limited. Baner, Pune 411045. View on Google Maps
- Launched
- 4 years 8 months originally promised
- Possession date (MahaRERA)
- 3 years 8 months awayExtended by 1 year (originally June 2029). Why possession dates change
- Concrete structure (RCC)
- 0%Early stageAverage across 2 buildings
- Units booked
- 244 of 27090% booked
Project facts
| 3 BHK | 257 |
|---|---|
| 4 BHK | 13 |
| Total units | 270 |
| Buildings | 2 |
| Land | 8.7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 2 |
Since Dec 2025: booked 195 → 244 · possession date June 2029 → June 2030 · complaints 1 → 2
Construction progress
As reported to MahaRERA at each updateWork not started as of Jul 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 244 | |
| 0% | 0% | 0% | 195 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Pune Baner Project-Tower 4 and 5 (MahaRERA PR1261012400049) is a residential project by Goel Ganga Ventures India Private Limited in Baner, Pune 411045. It was launched in October 2024. It has 270 units in 2 buildings, with 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2030, extended by 1 year from the original June 2029. Construction, averaged across its 2 buildings: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.
244 of its 270 units are booked (90%). Since the December 2025 update, 49 more units have been booked and the possession date has moved from June 2029 to June 2030.
Goel Ganga's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 61 |
|---|---|
| Completed without extending the possession date | 18 |
| Completed after an extension, or lapsed | 14 |
| Under construction | 29 |
| Possession date extended by the builder | 16 |
| Typical time from launch to 100% structure | 5 years 1 month |
| Complaints on MahaRERA, all Goel Ganga projects | 141 (27 of 61 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.