Wyce Exclucity, Bavdhan Budruk

by Saniket Infratech LLP. Bavdhan Budruk, Pune 411021. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2029No phase has an extended possession date
Concrete structure (RCC)
0%Early stage0 of 2 phases with structure completeWeighted across 2 phases
Units booked
125 of 36534% booked · 1 phase not reported
Price per sq ft
₹10,5002026 salesdown 6% on 2025See what buyers paid

Project facts

2 BHK106
3 BHK283
4 BHK72
Total units465
Buildings5
Land1.6 acres
Phases2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 810 sq ft₹79 – 90 lakh2026 sales
3 BHKabout 990 – 1,260 sq ft₹1.09 – 1.31 crore2026 sales
4 BHKabout 1,900 sq ft₹1.85 – 1.88 crore2026 sales

Price per sq ft, year by year

2025₹11,200 per sq ft
2026down 6% on 2025₹10,500 per sq ft

Registered sales across all 2 phases.

Compared with the typical Bavdhan Budruk rate in 2026: similar

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Wyce Exclucity C D
Early stage
P52100077762720%Not reported
Wyce Exclucity E F I
Early stage
P521000778273890%32%
Show updates by phase

Wyce Exclucity C D (P52100077762)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Wyce Exclucity E F I (P52100077827)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%125
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 4 similar projects in PIN 411021

Projects with 200–1,000 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 411021
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths5 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2029June 2029
Concrete structure (RCC)0%0%
Units booked34%58%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Wyce Exclucity is a project by Saniket Infratech LLP in Bavdhan Budruk, Pune 411021, registered with MahaRERA as 2 phases (P52100077762, P52100077827). The first phase was launched in October 2024. Together the phases have 465 units in 5 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. 0 of the 2 phases have their structure complete.

125 of the 365 units reported for sale are booked (34%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹10,500 per sq ft or less (down 6% on 2025), counting balconies and terrace in the size. Buyers here paid a rate similar to the typical Bavdhan Budruk rate in 2026. Most buyers paid ₹79–90 lakh for 2 BHK flats of about 810 sq ft (2026 sales); ₹1.09–1.31 crore for 3 BHK flats of about 990–1,260 sq ft (2026 sales); ₹1.85–1.88 crore for 4 BHK flats of about 1,900 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100077762 and P52100077827.Open MahaRERA and search P52100077762All projects in Bavdhan, Pashan, Sus