Skip to main content
← Back

Leela by Empyrean Landmarks Ph2, Kharadi

by Empyrean Landmarks. Kharadi, Pune 411014. View on Google Maps

Launched
3 years originally promised
Possession date (MahaRERA)
2 years 2 months awayExtended by 1 year (originally December 2027). Why possession dates change
Concrete structure (RCC)
23%Mid-constructionAverage across 2 buildings
Units booked
69 of 14448% booked
Price per sq ft (incl. balconies and terrace)
₹11,6002026 so far · 19 salesup 4% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK82
3 BHK62
Total units144
Buildings2
Land0.6 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 45 → 69 · structure 0% → 23% · possession date December 2027 → December 2028

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,040 sq ft₹1.20 – 1.24 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹11,200 per sq ft45 sales
2026 so farup 4% on 2025₹11,600 per sq ft19 sales

Rate vs other Kharadi projects, 2026: about 5% lower

Compared with 5 similar projects in PIN 411014

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411014
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs4 yrs 9 mths
Possession date extendedBy 1 year1 of 5
Possession date (MahaRERA)December 2028December 2029
Concrete structure (RCC) complete23%12%
Share of units booked48%29%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 10 months of the originally promised 3 years have passed
Concrete structure (RCC) 23% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jun 2025Dec 2025Jul 2026Dec 2024: Excavation 30%Jun 2025: Excavation 30%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jun 2025: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 23%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 23%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%23%0%69
100%0%0%45
30%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Leela by Empyrean Landmarks Ph2 (MahaRERA P52100078302) is a residential project by Empyrean Landmarks in Kharadi, Pune 411014. It was launched in December 2024. It has 144 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, extended by 1 year from the original December 2027. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) 23% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

69 of its 144 units are booked (48%). Since the December 2025 update, 24 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 23% and the possession date has moved from December 2027 to December 2028. 80% of the 2026 (so far) sales we found here were at ₹11,600 per sq ft or less (up 4% on 2025), counting balconies and terrace in the size, based on 19 registered sales. Buyers here paid a rate about 5% lower than at other Kharadi projects in 2026. Most buyers paid ₹1.20–1.24 crore for flats of 1,040 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100078302.Check it on MahaRERA (P52100078302)All projects in Kharadi, Vadgaon Sheri, Viman Nagar