Skip to main content
← Back

Regency Astra Phase IV, Baner

by Regency Aawishkar Sarsan Developers LLP. Baner, Pune 411045. View on Google Maps

Launched
1 year 5 months promised
Possession date (MahaRERA)
5 months awayPossession date unchanged since launch
Concrete structure (RCC)
75%Mid-construction
Units booked
Bookings not reported

Project facts

1 BHK146
Total units146
Buildings1
Land5.9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: structure 50% → 75% · total units 73 → 146

Share on WhatsApp

Compared with 6 similar projects in PIN 411045

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)1 yr 5 mths5 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)March 2027November 2030
Concrete structure (RCC) complete75%0%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year of the promised 1 year 5 months have passed
Concrete structure (RCC) 75% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 75%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%—
100%50%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Regency Astra Phase IV (MahaRERA P52100081020) is a residential project by Regency Aawishkar Sarsan Developers LLP in Baner, Pune 411045. It was launched in October 2025. It has 146 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 50% to 75%.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100081020.Check it on MahaRERA (P52100081020)All projects in Baner, Balewadi, Mahalunge