Life Republic Sector R5/5TH Avenue-canvas/phase-II, Jambhe

by Kolte-Patil Developers Limited. Jambhe, Pune 411033. View on Google Maps

Launched
5 years 2 months promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 2 buildings
Units booked
67 of 46115% booked
Price per sq ft (incl. balconies and terrace)
₹10,7002026 so far · 99 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK12
3 BHK321
4 BHK121
Other units (shops, offices or not given by type)7
Total units461
Buildings2
Land6.2 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,330 sq ft₹1.34 – 1.42 crore
1,450 – 1,500 sq ft₹1.50 – 1.64 crore
1,700 – 1,710 sq ft₹1.76 – 1.89 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹10,700 per sq ft99 sales

Rate vs other Jambhe projects, 2026: about 15% higher

Compared with 6 similar projects in PIN 411033

Projects with 200–1,000 flats, launched within 1 year of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths5 yrs
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2030December 2030
Concrete structure (RCC) complete0%0%
Share of units booked15%5%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year of the promised 5 years 2 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%67
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Life Republic Sector R5/5TH Avenue-canvas/phase-II (MahaRERA PM1260002501184) is a residential project by Kolte-Patil Developers Limited in Jambhe, Pune 411033. It was launched in October 2025. It has 461 units in 2 buildings: 454 homes (2, 3 & 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 2 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

67 of its 461 units are booked (15%). 80% of the 2026 (so far) sales we found here were at ₹10,700 per sq ft or less, counting balconies and terrace in the size, based on 99 registered sales. Buyers here paid a rate about 15% higher than at other Jambhe projects in 2026. Most buyers paid ₹1.34–1.42 crore for flats of 1,330 sq ft, ₹1.50–1.64 crore for 1,450–1,500 sq ft and ₹1.76–1.89 crore for 1,700–1,710 sq ft.

Kolte Patil's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA63
Completed without extending the possession date11
Completed after an extension, or lapsed17
Under construction35
Possession date extended by the builder4
Typical time from launch to 100% structure3 years
Complaints on MahaRERA, all Kolte Patil projects100 (28 of 63 projects)

See all Kolte Patil projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002501184.Check it on MahaRERA (PM1260002501184)All projects in Tathawade, Punawale, Jambhe