Sentosa Edge, Punawale

by Shree Balaji Associates. Punawale, Pune 411033. View on Google Maps

Launched
4 years 6 months promised
Possession date (MahaRERA)
3 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
18 of 3595% booked
Price per sq ft (incl. balconies and terrace)
₹8,5002026 so far · 221 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK186
3 BHK173
Total units359
Buildings3
Land2.3 acres
Reserved units24
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: total units 122 → 359

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
740 sq ft₹62 – 63 lakh
830 sq ft₹70 – 71 lakh
940 sq ft₹80 – 84 lakh
1,110 sq ft₹94 – 95 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹8,500 per sq ft221 sales

Rate vs other Punawale projects, 2026: about 5% lower

Compared with 6 similar projects in PIN 411033

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 6 mths5 yrs 6 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)June 2030June 2031
Concrete structure (RCC) complete0%0%
Share of units booked5%31%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
10 months of the promised 4 years 6 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 33%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 33%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
33%0%0%18
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Sentosa Edge (MahaRERA PM1260002501839) is a residential project by Shree Balaji Associates in Punawale, Pune 411033. It was launched in December 2025. It has 359 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

18 of its 359 units are booked (5%). 80% of the 2026 (so far) sales we found here were at ₹8,500 per sq ft or less, counting balconies and terrace in the size, based on 221 registered sales. Buyers here paid a rate about 5% lower than at other Punawale projects in 2026. Most buyers paid ₹62–63 lakh for flats of 740 sq ft, ₹70–71 lakh for 830 sq ft, ₹80–84 lakh for 940 sq ft and ₹94–95 lakh for 1,110 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PM1260002501839.Check it on MahaRERA (PM1260002501839)All projects in Tathawade, Punawale, Jambhe