Skip to main content
← Back

108 Astera "Wing D E & F", Punawale

by Aum Ventures. Punawale, Pune 411033. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
4 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 3 buildings
Units booked
98 of 23242% booked
Price per sq ft (incl. balconies and terrace)
₹9,1002026 so far · 78 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK144
3 BHK78
4 BHK10
Total units232
Buildings3
Land4.3 acres
Landowner share30
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
760 sq ft₹64 – 68 lakh
820 – 850 sq ft₹74 – 77 lakh
990 – 1,070 sq ft₹88 – 97 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹9,100 per sq ft78 sales

Rate vs other Punawale projects, 2026: similar

Compared with 6 similar projects in PIN 411033

Projects with 100–500 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2030September 2030
Concrete structure (RCC) complete0%0%
Share of units booked42%5%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
10 months of the promised 5 years have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 67%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 67%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%0%0%98
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

108 Astera "Wing D E & F" (MahaRERA PR1260002501838) is a residential project by Aum Ventures in Punawale, Pune 411033. It was launched in December 2025. It has 232 units in 3 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

98 of its 232 units are booked (42%). 80% of the 2026 (so far) sales we found here were at ₹9,100 per sq ft or less, counting balconies and terrace in the size, based on 78 registered sales. Buyers here paid a rate similar to other Punawale projects in 2026. Most buyers paid ₹64–68 lakh for flats of 760 sq ft, ₹74–77 lakh for 820–850 sq ft and ₹88–97 lakh for 990–1,070 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002501838.Check it on MahaRERA (PR1260002501838)All projects in Tathawade, Punawale, Jambhe