Kumar Parth Tower C3, Baner

by Kumar & Potnis Constructions LLP. Baner, Pune 411045. View on Google Maps

Launched
4 years 10 months promised
Possession date (MahaRERA)
3 years 7 months awayPossession date unchanged since launch
Concrete structure (RCC)
1%Mid-construction
Units booked
66 of 17438% booked
Price per sq ft (incl. balconies and terrace)
₹12,3002026 so far · 24 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK5
2 BHK95
3 BHK50
4 BHK24
Total units174
Buildings1
Land9 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: total units 122 → 174

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
770 sq ft₹90 – 96 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹12,300 per sq ft24 sales

Rate vs other Baner projects, 2026: similar

Compared with 6 similar projects in PIN 411045

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 10 mths5 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)May 2030September 2030
Concrete structure (RCC) complete1%0%
Share of units booked38%30%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 3 months of the promised 4 years 10 months have passed
Concrete structure (RCC) 1% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 1%Jul 2026: Concrete structure (RCC) 1%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 1%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%1%0%66
100%1%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Kumar Parth Tower C3 (MahaRERA PR1260002500333) is a residential project by Kumar & Potnis Constructions LLP in Baner, Pune 411045. It was launched in July 2025. It has 174 units in 1 building, with 1 RK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is May 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 1% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

66 of its 174 units are booked (38%). 80% of the 2026 (so far) sales we found here were at ₹12,300 per sq ft or less, counting balconies and terrace in the size, based on 24 registered sales. Buyers here paid a rate similar to other Baner projects in 2026. Most buyers paid ₹90–96 lakh for flats of 770 sq ft.

Kumar's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA82
Completed without extending the possession date42
Completed after an extension, or lapsed5
Under construction35
Possession date extended by the builder5
Typical time from launch to 100% structure2 years 6 months
Complaints on MahaRERA, all Kumar projects71 (8 of 82 projects)

See all Kumar projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1260002500333.Check it on MahaRERA (PR1260002500333)All projects in Baner, Balewadi, Mahalunge