Birla Evam Phase 1, Manjari Budruk

by Vypak Properties Private Limited. Manjari Budruk, Pune 412307. View on Google Maps

Launched
5 years 11 months promised
Possession date (MahaRERA)
4 years 8 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stageAverage across 4 buildings
Units booked
Bookings not reported
Price per sq ft (incl. balconies and terrace)
₹10,0002026 so far · 126 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK47
2 BHK466
3 BHK391
Other units (shops, offices or not given by type)24
Total units928
Buildings4
Land16.5 acres
Complaints on MahaRERA (filed by or against the builder)0
Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
710 – 720 sq ft₹67 – 71 lakh
790 – 810 sq ft₹74 – 81 lakh
910 – 960 sq ft₹80 – 96 lakh
1,090 – 1,120 sq ft₹81 lakh – ₹1.13 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2026 so far₹10,000 per sq ft126 sales

Rate vs other Manjari Budruk projects, 2026: about 15% higher

Compared with 3 similar projects in PIN 412307

Projects with 450–1,900 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 412307
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 11 mths5 yrs 2 mths
Possession date extendedNo1 of 3
Possession date (MahaRERA)June 2031September 2030
Concrete structure (RCC) complete0%0%
Complaints on MahaRERA (filed by or against the builder)01

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 3 months of the promised 5 years 11 months have passed
Concrete structure (RCC) 0% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Birla Evam Phase 1 (MahaRERA PR1261012500295) is a residential project by Vypak Properties Private Limited in Manjari Budruk, Pune 412307. It was launched in July 2025. It has 928 units in 4 buildings: 904 homes (1, 2 & 3 BHK) and 24 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2031, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

It has not reported any bookings to MahaRERA yet. 80% of the 2026 (so far) sales we found here were at ₹10,000 per sq ft or less, counting balconies and terrace in the size, based on 126 registered sales. Buyers here paid a rate about 15% higher than at other Manjari Budruk projects in 2026. Most buyers paid ₹67–71 lakh for flats of 710–720 sq ft, ₹74–81 lakh for 790–810 sq ft, ₹80–96 lakh for 910–960 sq ft and ₹81 lakh–₹1.13 crore for 1,090–1,120 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1261012500295.Check it on MahaRERA (PR1261012500295)All projects in Manjari, Shewalewadi