Sarita Niketan, Manjari Khurd
by Manjari Housing Projects LLP. Manjari Khurd, Pune 412307. View on Google Maps
- Launched
- 2 years 8 months originally promised
- Possession date (MahaRERA)
- 2 years 2 months awayExtended by 1 year (originally December 2027). Why possession dates change
- Concrete structure (RCC)
- 61%Mid-construction
- Units booked
- Bookings not reported
Project facts
| 1 BHK | 282 |
|---|---|
| 2 BHK | 194 |
| Total units | 476 |
| Buildings | 1 |
| Land | 1.3 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 28% → 61% · possession date December 2027 → December 2028
Compared with 4 similar projects in PIN 412307
Projects with 200–1,000 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 2 yrs 8 mths | 5 yrs 2 mths |
| Possession date extended | By 1 year | 0 of 4 |
| Possession date (MahaRERA) | December 2028 | September 2030 |
| Concrete structure (RCC) complete | 61% | 0% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Geras Avive Towers Phase I | July 2025 | September 2030 | 0% | 110 of 517 booked (21%) |
| VTP Aurelia Phase 1 | July 2025 | September 2030 | 0% | 376 of 901 booked (42%) |
| Birla Evam Phase 1 | July 2025 | June 2031 | 0% | Bookings not reported |
| Joyville Celestia Phase 6 | October 2024 | September 2029 | 0% | 169 of 592 booked (29%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 61% | 0% | — | |
| 100% | 28% | 0% | — | |
| 100% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
About this project
Sarita Niketan (MahaRERA P52100079924) is a residential project by Manjari Housing Projects LLP in Manjari Khurd, Pune 412307. It was launched in April 2025. It has 476 units in 1 building, with 1 & 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, extended by 1 year from the original December 2027. Construction: excavation complete, structure (RCC) 61% complete, final finishes not started. MahaRERA records do not show it as ready to move in.
It has not reported any bookings to MahaRERA yet. Since the December 2025 update, the reported concrete structure (RCC) has gone from 28% to 61% and the possession date has moved from December 2027 to December 2028.
Godrej's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 41 |
|---|---|
| Completed without extending the possession date | 9 |
| Completed after an extension, or lapsed | 2 |
| Under construction | 30 |
| Possession date extended by the builder | 11 |
| Typical time from launch to 100% structure | 3 years 4 months |
| Complaints on MahaRERA, all Godrej projects | 441 (35 of 41 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.