Rohan Harita Phase 3, Tathawade

by Rohan Builders & Developers Private Limited. Tathawade, Pune 411033. View on Google Maps

Launched
4 years 2 months promised
Possession date (MahaRERA)
3 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
0%Early stage
Units booked
92 of 14563% booked
Price per sq ft (incl. balconies and terrace)
₹11,0002026 so far · 89 salesup 1% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK17
2 BHK76
3 BHK52
Total units145
Buildings1
Land8.6 acres
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
720 sq ft₹73 – 76 lakh
1,100 sq ft₹1.19 – 1.23 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹10,900 per sq ft27 sales
2026 so farup 1% on 2025₹11,000 per sq ft89 sales

Rate vs other Tathawade projects, 2026: about 10% higher

Studios (under 450 sq ft)

80% of the 2025 studio sales we found were at this rate or less

2025₹10,700 per sq ft15 sales

Sizes 440 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 5 similar projects in PIN 411033

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 2 mths4 yrs 1 mth
Possession date extendedNo0 of 5
Possession date (MahaRERA)December 2029December 2029
Concrete structure (RCC) complete0%0%
Share of units booked63%31%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year of the promised 4 years 2 months have passed
Concrete structure (RCC) 0% complete

Work not started as of Jul 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%92
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Rohan Harita Phase 3 (MahaRERA PR1263032501085) is a residential project by Rohan Builders & Developers Private Limited in Tathawade, Pune 411033. It was launched in October 2025. It has 145 units in 1 building, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started. MahaRERA records do not show it as ready to move in.

92 of its 145 units are booked (63%). 80% of the 2026 (so far) sales we found here were at ₹11,000 per sq ft or less (up 1% on 2025), counting balconies and terrace in the size, based on 89 registered sales. Buyers here paid a rate about 10% higher than at other Tathawade projects in 2026. Most buyers paid ₹73–76 lakh for flats of 720 sq ft and ₹1.19–1.23 crore for 1,100 sq ft. Its studios (under 450 sq ft) sold at ₹10,700 per sq ft or less in 2025 (15 sales); studios are priced separately from flats.

Rohan's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA32
Completed without extending the possession date16
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 8 months
Complaints on MahaRERA, all Rohan projects17 (11 of 32 projects)

See all Rohan projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration PR1263032501085.Check it on MahaRERA (PR1263032501085)All projects in Tathawade, Punawale, Jambhe