Rohan Harita Phase 2, Tathawade

by Rohan Builders & Developers Private Limited. Tathawade, Pune 411033. View on Google Maps

Launched
3 years 9 months promised
Possession date (MahaRERA)
2 years 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
43%Mid-constructionAverage across 3 buildings
Units booked
340 of 35297% booked
Price per sq ft (incl. balconies and terrace)
₹10,9002026 so far · 32 salesup 7% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK38
2 BHK172
3 BHK142
Total units352
Buildings3
Land8.6 acres
Reserved units1
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 271 → 340 · structure 13% → 43% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
710 – 830 sq ft₹74 – 81 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹10,200 per sq ft283 sales
2026 so farup 7% on 2025₹10,900 per sq ft32 sales

Rate vs other Tathawade projects, 2026: about 10% higher

Studios (under 450 sq ft)

80% of the 2025 studio sales we found were at this rate or less

2025₹10,000 per sq ft36 sales

Sizes 440 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 6 similar projects in PIN 411033

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 9 mths4 yrs 5 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)December 2028August 2029
Concrete structure (RCC) complete43%4%
Share of units booked97%60%
Complaints on MahaRERA (filed by or against the builder)10

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
1 year 7 months of the promised 3 years 9 months have passed
Concrete structure (RCC) 43% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jun 2025Dec 2025Jul 2026Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Jun 2025: Concrete structure (RCC) 7%Dec 2025: Concrete structure (RCC) 13%Jul 2026: Concrete structure (RCC) 43%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 43%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%43%0%340
100%13%0%271
100%7%0%271

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Rohan Harita Phase 2 (MahaRERA P52100079539) is a residential project by Rohan Builders & Developers Private Limited in Tathawade, Pune 411033. It was launched in March 2025. It has 352 units in 3 buildings, with 1, 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2028, unchanged since launch. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) 43% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

340 of its 352 units are booked (97%). Since the December 2025 update, 69 more units have been booked and the reported concrete structure (RCC) has gone from 13% to 43%. 80% of the 2026 (so far) sales we found here were at ₹10,900 per sq ft or less (up 7% on 2025), counting balconies and terrace in the size, based on 32 registered sales. Buyers here paid a rate about 10% higher than at other Tathawade projects in 2026. Most buyers paid ₹74–81 lakh for flats of 710–830 sq ft. Its studios (under 450 sq ft) sold at ₹10,000 per sq ft or less in 2025 (36 sales); studios are priced separately from flats.

Rohan's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA32
Completed without extending the possession date16
Completed after an extension, or lapsed4
Under construction12
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 8 months
Complaints on MahaRERA, all Rohan projects17 (11 of 32 projects)

See all Rohan projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100079539.Check it on MahaRERA (P52100079539)All projects in Tathawade, Punawale, Jambhe