Skip to main content
← Back

ANP Memento, Wakad

Finishing stage

Final finishes 100% · completion not yet filed on MahaRERA

by Five Star Construction Company. Wakad, Pune 411057. View on Google Maps

Launched
6 years 1 month promised
Possession date (MahaRERA)
1 month agoPossession date unchanged since launch
Concrete structure (RCC)
100%Finishing stageAverage across 4 buildings
Units booked
338 of 36892% booked

Project facts

2 BHK148
3 BHK172
4 BHK48
Total units368
Buildings4
Land2.1 acres
Landowner share22
Complaints on MahaRERA (filed by or against the builder)14

Since Dec 2025: booked 336 → 338 · final finishes 75% → 100% · complaints 12 → 14

Share on WhatsApp

Compared with 5 similar projects in PIN 411057

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 1 mth6 yrs 7 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)September 2026June 2027
Concrete structure (RCC) complete100%67%
Share of units booked92%78%
Complaints on MahaRERA (filed by or against the builder)140

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the promised 6 years 1 month have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 61%Jun 2024: Concrete structure (RCC) 61%Dec 2024: Concrete structure (RCC) 100%Jun 2025: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 75%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%338
100%100%75%336
100%100%0%330
100%61%0%249

"—" means MahaRERA shows no figure for that update.

About this project

ANP Memento (MahaRERA P52100026219) is a residential project by Five Star Construction Company in Wakad, Pune 411057. It was launched in August 2020. It has 368 units in 4 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is September 2026, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete (structure and final finishes), but completion has not yet been recorded on MahaRERA.

338 of its 368 units are booked (92%). Since the December 2025 update, 2 more units have been booked.

ANP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA10
Completed without extending the possession date1
Completed after an extension, or lapsed3
Under construction6
Possession date extended by the builder1
Typical time from launch to 100% structure2 years 10 months
Complaints on MahaRERA, all ANP projects17 (2 of 10 projects)

See all ANP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100026219.Check it on MahaRERA (P52100026219)All projects in Wakad, Hinjewadi, Marunji