The Legend Phase II, Hinjewadi
by Shree Sankalp Associates. Hinjewadi, Pune 411057. View on Google Maps
- Launched
- 3 years 10 months originally promised
- Possession date (MahaRERA)
- 4 months ago. No further extension recordedExtended by 2 years (originally June 2024). Why possession dates change
- Concrete structure (RCC)
- 33%Mid-constructionAverage across 3 buildings
- Units booked
- 149 of 24461% booked
Project facts
| 1 RK | 59 |
|---|---|
| 1 BHK | 54 |
| 2 BHK | 112 |
| Other units (shops, offices or not given by type) | 19 |
| Total units | 244 |
| Buildings | 3 |
| Land | 2.6 acres |
| Landowner share | 56 |
| Complaints on MahaRERA (filed by or against the builder) | 1 |
Since Dec 2025: booked 142 → 149 · final finishes 23% → 33%
Compared with 5 similar projects in PIN 411057
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs 10 mths | 6 yrs 7 mths |
| Possession date extended | By 2 years | 1 of 5 |
| Possession date passed | Yes, due June 2026 | 1 ready to move; 0 also past their date |
| Concrete structure (RCC) complete | 33% | 67% |
| Share of units booked | 61% | 78% |
| Complaints on MahaRERA (filed by or against the builder) | 1 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sukhwani Ambar | October 2020 | June 2027 | 18% | 87 of 358 booked (24%) |
| Ira | April 2020 | September 2027 | 0% | Bookings not reported |
| Ganga Asmi | December 2020 | June 2027 | 67% | 244 of 255 booked (96%) |
| Livmo Phase I | March 2020 | December 2024 | 100% | 220 of 234 booked (94%) |
| Park 59 | February 2020 | September 2026 | 100% | 144 of 230 booked (63%) |
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 33% | 33% | 149 | |
| 33% | 33% | 23% | 142 | |
| 100% | 100% | 70% | 123 | |
| 100% | 70% | 0% | 91 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
The Legend Phase II (MahaRERA P52100025986) is a residential project by Shree Sankalp Associates in Hinjewadi, Pune 411057. It was launched in August 2020. It has 244 units in 3 buildings: 225 homes (1 RK, 1 BHK & 2 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in June 2026, after an extension of 2 years from the original June 2024. That date has passed and no further extension has been recorded. Construction, averaged across its 3 buildings: excavation 67% complete, structure (RCC) 33% complete, final finishes 33% complete. MahaRERA records do not show it as ready to move in.
149 of its 244 units are booked (61%). Since the December 2025 update, 7 more units have been booked.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.