Livmo, Bhoirwadi

Ready to moveLapsed

by Priyanka Builders. Bhoirwadi, Pune 411057. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2024 – Dec 2025varies by phase2 of 2 phases have an extended possession date. What does Lapsed mean?
Concrete structure (RCC)
100%Ready to move2 of 2 phases with structure completeWeighted across 2 phases
Units booked
370 of 43086% booked

Project facts

1 BHK220
2 BHK196
Total units430
Buildings3
Land2.2 acres
Phases2
Share on WhatsApp

Shortlist 2 or more to compare side by side.

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Livmo Phase I
Ready to move Lapsed
P52100025084220100%94%
Livmo Phase II
Ready to move Lapsed
P52100049773196100%77%
Show updates by phase

Livmo Phase I (P52100025084)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%220
100%100%98%220
100%100%20%220
100%100%10%219
100%80%0%212

"—" means MahaRERA shows no figure for that update.

Livmo Phase II (P52100049773)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%94%150
100%100%78%150
100%100%25%151
100%100%10%136
100%100%0%65

"—" means MahaRERA shows no figure for that update.

Compared with 4 similar projects in PIN 411057

Projects with 200–900 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)2 yrs 10 mths7 yrs
Possession date extendedYes0 of 4
Possession date (MahaRERA)Dec 2024 – Dec 2025March 2027
Concrete structure (RCC)100%100%
Units booked86%98%
MahaRERA complaints (filed by or against the builder)70

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Livmo is a project by Priyanka Builders in Bhoirwadi, Pune 411057, registered with MahaRERA as 2 phases (P52100025084, P52100049773). The first phase was launched in March 2020. Together the phases have 430 units in 3 buildings, with 1 & 2 BHK homes as registered with MahaRERA. All 2 phases are lapsed on MahaRERA.

The phases' registered possession dates run from December 2024 to December 2025; 2 of 2 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 92% complete. 2 of the 2 phases have their structure complete.

370 of the 430 units reported for sale are booked (86%).

Source: MahaRERA registrations P52100025084 and P52100049773.Open MahaRERA and search P52100025084All projects in Wakad, Hinjewadi, Marunji