Ganga Asmi, Wakad
by Shanti Mohan Developers LLP. Wakad, Pune 411057. View on Google Maps
- Launched
- 6 years 6 months promised
- Possession date (MahaRERA)
- 8 months awayPossession date unchanged since launch
- Concrete structure (RCC)
- 67%Mid-constructionAverage across 3 buildings
- Units booked
- 244 of 25596% booked
Project facts
| 2 BHK | 150 |
|---|---|
| 3 BHK | 105 |
| Total units | 255 |
| Buildings | 3 |
| Land | 7 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: structure 61% → 67% · final finishes 0% → 4%
Compared with 6 similar projects in PIN 411057
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 6 yrs 6 mths | 5 yrs 4 mths |
| Possession date extended | No | 3 of 6 |
| Possession date (MahaRERA) | June 2027 | June 2027 |
| Concrete structure (RCC) complete | 67% | 54% |
| Share of units booked | 96% | 71% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Sukhwani Ambar | October 2020 | June 2027 | 18% | 87 of 358 booked (24%) |
| Kamalaraj Athens B and C | April 2021 | June 2027 | 100% | 139 of 182 booked (76%) |
| The Legend Phase II | August 2020 | June 2026 | 33% | 149 of 244 booked (61%) |
| ANP Memento | August 2020 | September 2026 | 100% | 338 of 368 booked (92%) |
| Trident E F | May 2021 | December 2027 | 15% | 198 of 302 booked (66%) |
| Sportsville | June 2021 | December 2026 | 75% | 431 of 459 booked (94%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 33% | 67% | 4% | 244 | |
| 33% | 61% | 0% | 244 | |
| 33% | 26% | 0% | 244 | |
| 33% | 10% | 0% | 242 | |
| 33% | 4% | 0% | 235 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Ganga Asmi (MahaRERA P52100027644) is a residential project by Shanti Mohan Developers LLP in Wakad, Pune 411057. It was launched in December 2020. It has 255 units in 3 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 3 buildings: excavation 33% complete, structure (RCC) 67% complete, final finishes 4% complete. MahaRERA records do not show it as ready to move in.
244 of its 255 units are booked (96%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 61% to 67%.
Goel Ganga's track record in Pune
MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers
| Projects registered with MahaRERA | 61 |
|---|---|
| Completed without extending the possession date | 18 |
| Completed after an extension, or lapsed | 14 |
| Under construction | 29 |
| Possession date extended by the builder | 16 |
| Typical time from launch to 100% structure | 5 years 1 month |
| Complaints on MahaRERA, all Goel Ganga projects | 141 (27 of 61 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not extend its possession date. MahaRERA's COVID extensions (6 + 6 months, 2020–21) are not counted as the builder's.
- Completed after an extension, or lapsed: every other registration that is not under construction.
- Under construction: MahaRERA status Active.
- Possession date extended by the builder: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure reached 100% between December 2023 and July 2026, counted from registration.
- Complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.