Sukhwani Ambar, Wakad

by Sukhwani Developers. Wakad, Pune 411057. View on Google Maps

Launched
6 years 8 months promised
Possession date (MahaRERA)
8 months awayPossession date unchanged since launch
Concrete structure (RCC)
18%Mid-constructionAverage across 5 buildings
Units booked
87 of 35824% booked
Price per sq ft (incl. balconies and terrace)
₹11,5002026 so far · 10 salesup 17% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK32
2 BHK152
3 BHK154
Other units (shops, offices or not given by type)20
Total units358
Buildings5
Land2.8 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 61 → 87 · structure 3% → 18%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
790 – 800 sq ft₹68 – 79 lakh
1,160 sq ft₹1.09 – 1.18 crore

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,000 per sq ft26 sales
2025down 2% on 2024₹9,800 per sq ft15 sales
2026 so farup 17% on 2025₹11,500 per sq ft10 sales

Rate vs other Wakad projects, 2026: similar

Compared with 5 similar projects in PIN 411057

Projects with 150–700 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)6 yrs 8 mths6 yrs 2 mths
Possession date extendedNo1 of 5
Possession date (MahaRERA)June 2027June 2027
Concrete structure (RCC) complete18%67%
Share of units booked24%84%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
6 years of the promised 6 years 8 months have passed
Concrete structure (RCC) 18% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 0%Dec 2024: Excavation 40%Jun 2025: Excavation 40%Dec 2025: Excavation 40%Jul 2026: Excavation 40%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 0%Dec 2024: Concrete structure (RCC) 3%Jun 2025: Concrete structure (RCC) 3%Dec 2025: Concrete structure (RCC) 3%Jul 2026: Concrete structure (RCC) 18%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 40%Concrete structure (RCC) 18%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
40%18%0%87
40%3%0%61
40%3%0%25
0%0%0%—

"—" means MahaRERA shows no figure for that update.

About this project

Sukhwani Ambar (MahaRERA P52100026576) is a residential project by Sukhwani Developers in Wakad, Pune 411057. It was launched in October 2020. It has 358 units in 5 buildings: 338 homes (1, 2 & 3 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction, averaged across its 5 buildings: excavation 40% complete, structure (RCC) 18% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

87 of its 358 units are booked (24%). Since the December 2025 update, 26 more units have been booked and the reported concrete structure (RCC) has gone from 3% to 18%. 80% of the 2026 (so far) sales we found here were at ₹11,500 per sq ft or less (up 17% on 2025), counting balconies and terrace in the size, based on 10 registered sales. Buyers here paid a rate similar to other Wakad projects in 2026. Most buyers paid ₹68–79 lakh for flats of 790–800 sq ft and ₹1.09–1.18 crore for 1,160 sq ft.

Sukhwani's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA28
Completed without extending the possession date14
Completed after an extension, or lapsed3
Under construction11
Possession date extended by the builder4
Complaints on MahaRERA, all Sukhwani projects10 (4 of 28 projects)

See all Sukhwani projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100026576.Check it on MahaRERA (P52100026576)All projects in Wakad, Hinjewadi, Marunji