Skip to main content
← Back

Fairmont, Wakad

by Krishna Icon Skyscraper LLP. Wakad, Pune 411057. View on Google Maps

Launched
3 years 11 months originally promised
Possession date (MahaRERA)
2 months agoExtended by 1 year (originally August 2025). Why possession dates change
Concrete structure (RCC)
100%Nearing possessionAverage across 3 buildings
Units booked
141 of 24657% booked
Price per sq ft (incl. balconies and terrace)
₹11,2002026 so far · 41 salesup 9% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK24
1 BHK4
2 BHK136
3 BHK70
4 BHK3
Other units (shops, offices or not given by type)9
Total units246
Buildings3
Land1.5 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 115 → 141 · structure 33% → 100% · final finishes 20% → 83%

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
770 – 800 sq ft₹77 – 90 lakh
1,070 sq ft₹1.06 – 1.18 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2025₹10,300 per sq ft35 sales
2026 so farup 9% on 2025₹11,200 per sq ft41 sales

Rate vs other Wakad projects, 2026: similar

Compared with 6 similar projects in PIN 411057

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)3 yrs 11 mths3 yrs 8 mths
Possession date extendedBy 1 year4 of 6
Possession date (MahaRERA)August 2026December 2026
Concrete structure (RCC) complete100%100%
Share of units booked57%94%
Complaints on MahaRERA (filed by or against the builder)02

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 3 years 11 months have passed
Concrete structure (RCC) 100% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 0%Jun 2024: Excavation 67%Dec 2024: Excavation 67%Jun 2025: Excavation 67%Dec 2025: Excavation 67%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 27%Dec 2024: Concrete structure (RCC) 27%Jun 2025: Concrete structure (RCC) 27%Dec 2025: Concrete structure (RCC) 33%Jul 2026: Concrete structure (RCC) 100%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 20%Jul 2026: Final finishes 83%Excavation 100%Concrete structure (RCC) 100%Final finishes 83%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%83%141
67%33%20%115
67%27%0%91
0%0%0%28

"—" means MahaRERA shows no figure for that update.

About this project

Fairmont (MahaRERA P52100030773) is a residential project by Krishna Icon Skyscraper LLP in Wakad, Pune 411057. It was launched in September 2021. It has 246 units in 3 buildings: 237 homes (1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is August 2026, extended by 1 year from the original August 2025. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 83% complete. MahaRERA records do not show it as ready to move in.

141 of its 246 units are booked (57%). Since the December 2025 update, 26 more units have been booked and the reported concrete structure (RCC) has gone from 33% to 100%. 80% of the 2026 (so far) sales we found here were at ₹11,200 per sq ft or less (up 9% on 2025), counting balconies and terrace in the size, based on 41 registered sales. Buyers here paid a rate similar to other Wakad projects in 2026. Most buyers paid ₹77–90 lakh for flats of 770–800 sq ft and ₹1.06–1.18 crore for 1,070 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100030773.Check it on MahaRERA (P52100030773)All projects in Wakad, Hinjewadi, Marunji