Skip to main content

The Canary, Balewadi

by Grow India Nirmiti LLP. Balewadi, Pune 411045. View on Google Maps

Launched
First of 3 phases
Possession dates (MahaRERA)
Dec 2026 – Dec 2027varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
87%Mid-construction1 of 3 phases with structure completeWeighted across 3 phases
Units booked
732 of 94677% booked
Price per sq ft
₹13,8002026 salesup 5% on 2025See what buyers paid

Project facts

2 BHK421
3 BHK440
4 BHK85
Total units946
Buildings10
Land0.4 acres
Phases3

Since Dec 2025: booked 726 → 732

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 830 sq ft₹1.14 – 1.15 crore2026 sales
3 BHKabout 1,110 – 1,200 sq ft₹1.51 – 1.62 crore2026 sales
4 BHKabout 1,440 sq ft₹1.90 – 1.95 crore2026 sales

Price per sq ft, year by year

2023₹11,400 per sq ft
2024up 12% on 2023₹12,800 per sq ft
2025up 2% on 2024₹13,100 per sq ft
2026up 5% on 2025₹13,800 per sq ft

Registered sales across all 3 phases.

Compared with the typical Balewadi rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Canary Phase I
Nearing possession
P52100031557360100%85%
The Canary Phase 2
Mid-construction
P5210003385042080%86%
The Canary Phase 3
Mid-construction
P5210005184516674%39%
Show updates by phase

The Canary Phase I (P52100031557)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%31%306
100%100%22%306
100%100%19%354
100%100%16%354
100%81%0%354

"—" means MahaRERA shows no figure for that update.

The Canary Phase 2 (P52100033850)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%80%12%362
80%66%6%362
80%38%4%345
80%21%3%325
80%14%0%306

"—" means MahaRERA shows no figure for that update.

The Canary Phase 3 (P52100051845)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%74%4%64
100%50%1%58
100%39%0%35
100%8%0%4
50%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 4 similar projects in PIN 411045

Projects with 450–1,900 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 2 mths4 yrs 5 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2026 – Dec 2027December 2026
Concrete structure (RCC)87%92%
Units booked77%86%
MahaRERA complaints (filed by or against the builder)02

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

The Canary is a project by Grow India Nirmiti LLP in Balewadi, Pune 411045, registered with MahaRERA as 3 phases (P52100031557, P52100033850, P52100051845). The first phase was launched in October 2021. Together the phases have 946 units in 10 buildings, with 2, 3 & 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.

The phases' registered possession dates run from December 2026 to December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 87% complete and final finishes 18% complete. 1 of the 3 phases have their structure complete.

732 of the 946 units reported for sale are booked (77%). In 2026 registered sales, 80% of flats here sold at ₹13,800 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Balewadi rate in 2026. Most buyers paid ₹1.14–1.15 crore for 2 BHK flats of about 830 sq ft (2026 sales); ₹1.51–1.62 crore for 3 BHK flats of about 1,110–1,200 sq ft (2026 sales); ₹1.90–1.95 crore for 4 BHK flats of about 1,440 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100031557, P52100033850 and P52100051845.Open MahaRERA and search P52100031557All projects in Baner, Balewadi, Mahalunge