Majestique Signature Towers, Balewadi
by Majestique Homes LLP. Balewadi, Pune 411045. View on Google Maps
- Launched
- First of 5 phases
- Possession dates (MahaRERA)
- Dec 2026 – Dec 2028varies by phaseNo phase has an extended possession date
- Concrete structure (RCC)
- 78%Mid-construction4 of 5 phases with structure completeWeighted across 5 phases
- Units booked
- 416 of 50682% booked
- Price per sq ft
- ₹15,7002026 salesup 5% on 2025See what buyers paid
Facts
Project facts
| 2 BHK | 333 |
|---|---|
| 3 BHK | 225 |
| Total units | 558 |
| Buildings | 5 |
| Land | 1.2 acres |
| Phases | 5 |
Since Dec 2025: booked 344 → 317
Shortlist 2 or more to compare side by side.
Prices
What buyers paid here
From government sale recordsWhat buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.
Flat types, sizes and prices
| Flat type | Size (total internal area) | What most buyers paid | Year |
|---|---|---|---|
| 2 BHK | about 810 – 830 sq ft | ₹98 lakh – ₹1.26 crore | 2026 sales |
| 3 BHK | about 1,260 – 1,290 sq ft | ₹1.83 – 2.05 crore | 2026 sales |
Price per sq ft, year by year
| 2023 | ₹13,800 per sq ft |
|---|---|
| 2024down 2% on 2023 | ₹13,500 per sq ft |
| 2025up 11% on 2024 | ₹15,000 per sq ft |
| 2026up 5% on 2025 | ₹15,700 per sq ft |
Registered sales across all 5 phases.
Compared with the typical Balewadi rate in 2026: about 5% higher
How to read this price
- 80% of registered sales that year were at this rate or less.
- Size is total internal area: carpet + balcony + terrace.
- Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
- The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
- Fewer sales means a less certain figure.
- Use it as a starting point for questions, not as an offer price.
Phases
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Majestique Signature Towers B3 Ready to move | P52100033023 | 73 | 100% | 85% | |
| Majestique Signature Towers B2 Ready to move | P52100033440 | 73 | 100% | 78% | |
| Majestique Signature Towers B1 Ready to move | P52100046347 | 76 | 100% | 92% | |
| Majestique Signature Towers A1 Nearing possession | P52100051835 | 149 | 100% | 86% | |
| Majestique Signature Towers, Building NO B, Wing B6 Mid-construction | P52100076891 | 187 | 35% | 53% |
Show updates by phase
Majestique Signature Towers B3 (P52100033023)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 62 | |
| 100% | 100% | 10% | 67 | |
| 100% | 80% | 0% | 67 |
"—" means MahaRERA shows no figure for that update.
Majestique Signature Towers B2 (P52100033440)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 57 | |
| 100% | 100% | 10% | 73 | |
| 100% | 80% | 0% | 71 |
"—" means MahaRERA shows no figure for that update.
Majestique Signature Towers B1 (P52100046347)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 70 | |
| 100% | 100% | 0% | 76 | |
| 100% | 50% | 0% | 76 | |
| 100% | 0% | 0% | 66 |
"—" means MahaRERA shows no figure for that update.
Majestique Signature Towers A1 (P52100051835)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 128 | |
| 100% | 55% | 0% | 128 | |
| 100% | 60% | 0% | 105 | |
| 100% | 10% | 0% | 105 | |
| 0% | 0% | 0% | 50 |
"—" means MahaRERA shows no figure for that update.
Majestique Signature Towers, Building NO B, Wing B6 (P52100076891)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 99 | |
| 90% | 0% | 0% | — | |
| 0% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Compare
Compared with 6 similar projects in PIN 411045
Projects with 250–1,200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 4 yrs 6 mths | 4 yrs 10 mths |
| Possession date extended | No | 2 of 6 |
| Possession date (MahaRERA) | Dec 2026 – Dec 2028 | December 2026 |
| Concrete structure (RCC) | 78% | 91% |
| Units booked | 82% | 76% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Kalpataru Jade Skyline | March 2022 | December 2026 | 74% | 315 of 465 booked (68%) |
| Regency Astra | December 2021 | Nov 2025 – Dec 2028 | 95% | 520 of 704 booked (74%) |
| The Midas Residences | June 2022 | Jun 2028 – Jun 2030 | 0% | 224 of 360 booked (62%) |
| The Canary | October 2021 | Dec 2026 – Dec 2027 | 87% | 732 of 946 booked (77%) |
| ANP Universe | August 2021 | December 2026 | 100% | 530 of 610 booked (87%) |
| Supreme Estia | August 2021 | Dec 2025 | 100% | 370 of 375 booked (99%) |
How to read construction stages
- Early stage
- The concrete structure (RCC) has not started yet.
- Mid-construction
- The concrete structure (RCC) is being built.
- Nearing possession
- The concrete structure (RCC) is complete and final finishes are below 90%.
- Ready to move
- MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
- Concrete structure (RCC)
- The reinforced-concrete frame of the building: columns, beams and slabs.
- Final finishes
- Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- Lapsed
- MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.
About this project
Majestique Signature Towers is a project by Majestique Homes LLP in Balewadi, Pune 411045, registered with MahaRERA as 5 phases (P52100033023, P52100033440, P52100046347, P52100051835, P52100076891). The first phase was launched in February 2022. Together the phases have 558 units in 5 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 5 phases are active on MahaRERA.
The phases' registered possession dates run from December 2026 to December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 78% complete and final finishes 40% complete. 4 of the 5 phases have their structure complete.
416 of the 506 units reported for sale are booked (82%). In 2026 registered sales, 80% of flats here sold at ₹15,700 per sq ft or less (up 5% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% higher than the typical Balewadi rate in 2026. Most buyers paid ₹98 lakh–₹1.26 crore for 2 BHK flats of about 810–830 sq ft (2026 sales); ₹1.83–2.05 crore for 3 BHK flats of about 1,260–1,290 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
Majestique's track record in Pune
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Projects registered with MahaRERA | 74 |
|---|---|
| Completed without extending the possession date | 35 |
| Completed after an extension | 0 |
| Lapsed | 9 |
| Under construction | 30 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 3 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Majestique projects | 30 (11 of 74 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and July 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.