Venkatesh Erandwane Central - BUILDING-B2 - Phase 3

by Shree Venkatesh Buildcon PVT Ltd. Erandwane, Pune 411004. View on Google Maps

Launched
5 years promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
62%Mid-construction
Units booked
69 of 11461% booked
Price per sq ft (incl. balconies and terrace)
₹23,7002026 so far · 11 salesabout the same as 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK2
2 BHK1
3 BHK6
4 BHK105
Total units114
Buildings1
Land1 acre
Complaints on MahaRERA (filed by or against the builder)1

Since Dec 2025: booked 65 → 69 · structure 95% → 62% · final finishes 39% → 12% · complaints 0 → 1

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,670 sq ft₹3.64 – 3.98 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹23,300 per sq ft19 sales
2025up 1% on 2024₹23,600 per sq ft26 sales
2026 so farabout the same as 2025₹23,700 per sq ft11 sales

Rate vs other Erandwane projects, 2026: about 10% higher

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 10 months of the promised 5 years have passed
Concrete structure (RCC) 62% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 10%Dec 2024: Concrete structure (RCC) 32%Jun 2025: Concrete structure (RCC) 32%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 62%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 4%Jun 2025: Final finishes 4%Dec 2025: Final finishes 39%Jul 2026: Final finishes 12%Excavation 100%Concrete structure (RCC) 62%Final finishes 12%

If a percentage drops between updates, we show it as MahaRERA reported it.

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%62%12%69
100%95%39%65
100%32%4%44
100%10%0%31
100%0%0%25

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

Venkatesh Erandwane Central - BUILDING-B2 - Phase 3 (MahaRERA P52100032017) is a residential project by Shree Venkatesh Buildcon PVT Ltd in Erandwane, Pune 411004. It was launched in December 2021. It has 114 units in 1 building, with 1 RK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 62% complete, final finishes 12% complete. MahaRERA records do not show it as ready to move in.

69 of its 114 units are booked (61%). Since the December 2025 update, 4 more units have been booked and the reported concrete structure (RCC) has gone from 95% to 62%. 80% of the 2026 (so far) sales we found here were at ₹23,700 per sq ft or less (about the same as 2025), counting balconies and terrace in the size, based on 11 registered sales. Buyers here paid a rate about 10% higher than at other Erandwane projects in 2026. Most buyers paid ₹3.64–3.98 crore for flats of 1,670 sq ft.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100032017.Check it on MahaRERA (P52100032017)All projects in Deccan