Venkatesh Erandwane Central - BUILDING-B1 - Phase 2
by Shree Venkatesh Buildcon PVT Ltd. Erandwane, Pune 411004. View on Google Maps
- Launched
- 4 years 8 months promised
- Possession date (MahaRERA)
- 1 month agoPossession date unchanged since launch
- Concrete structure (RCC)
- 76%Mid-construction
- Units booked
- 144 of 17483% booked
- Price per sq ft (incl. balconies and terrace)
- ₹22,7002025 · 13 salesdown 2% on 202480% of the 2025 sales we found were at this rate or lessSee what buyers paid
Project facts
| 2 BHK | 116 |
|---|---|
| 3 BHK | 58 |
| Total units | 174 |
| Buildings | 1 |
| Land | 1 acre |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 145 → 144 · structure 100% → 76% · final finishes 51% → 12%
What buyers paid here
From government sale recordsThe price per sq ft is the agreed price of the flat alone, counting balconies and terrace.
Price per sq ft, year by year
80% of the flats sold in each year went for this price or less.
| 2024 | ₹23,100 per sq ft | 22 sales |
|---|---|---|
| 2025down 2% on 2024 | ₹22,700 per sq ft | 13 sales |
Rate vs other Erandwane projects, 2025: about 25% higher
Construction progress
As reported to MahaRERA at each updateIf a percentage drops between updates, we show it as MahaRERA reported it.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 76% | 12% | 144 | |
| 100% | 100% | 51% | 145 | |
| 100% | 41% | 4% | 129 | |
| 100% | 10% | 0% | 120 | |
| 100% | 0% | 0% | 102 |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
Venkatesh Erandwane Central - BUILDING-B1 - Phase 2 (MahaRERA P52100032631) is a residential project by Shree Venkatesh Buildcon PVT Ltd in Erandwane, Pune 411004. It was launched in January 2022. It has 174 units in 1 building, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 76% complete, final finishes 12% complete. MahaRERA records do not show it as ready to move in.
144 of its 174 units are booked (83%). Since the December 2025 update, the reported concrete structure (RCC) has gone from 100% to 76%. 80% of the 2025 sales we found here were at ₹22,700 per sq ft or less (down 2% on 2024), counting balconies and terrace in the size, based on 13 registered sales. Buyers here paid a rate about 25% higher than at other Erandwane projects in 2025.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.