Kalpataru Jade Skyline, Baner

by Astrum Developments Private Limited. Baner, Pune 411045. View on Google Maps

Launched
4 years 9 months promised
Possession date (MahaRERA)
2 months awayPossession date unchanged since launch
Concrete structure (RCC)
74%Mid-construction
Units booked
315 of 46568% booked
Price per sq ft (incl. balconies and terrace)
₹14,8002026 so far · 46 salesup 2% on 202580% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 RK72
1 BHK38
2 BHK89
3 BHK262
4 BHK4
Total units465
Buildings1
Land0.4 acres
Complaints on MahaRERA (filed by or against the builder)2

Since Dec 2025: booked 279 → 315 · complaints 0 → 2

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
1,190 sq ft₹1.64 – 1.80 crore

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹14,300 per sq ft74 sales
2025up 1% on 2024₹14,500 per sq ft91 sales
2026 so farup 2% on 2025₹14,800 per sq ft46 sales

Rate vs other Baner projects, 2026: about 20% higher

Studios (under 450 sq ft)

80% of the 2026 studio sales we found were at this rate or less

2024₹16,100 per sq ft30 sales
2025up 1% on 2024₹16,300 per sq ft34 sales
2026 so fardown 1% on 2025₹16,200 per sq ft33 sales

Sizes 350 sq ft. Studios are priced separately from flats and are not used in area price comparisons or Data Analytics.

Compared with 5 similar projects in PIN 411045

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 9 mths5 yrs 2 mths
Possession date extendedNo2 of 5
Possession date (MahaRERA)December 2026December 2027
Concrete structure (RCC) complete74%80%
Share of units booked68%85%
Complaints on MahaRERA (filed by or against the builder)20

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
4 years 7 months of the promised 4 years 9 months have passed
Concrete structure (RCC) 74% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 97%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 0%Jun 2024: Concrete structure (RCC) 24%Dec 2024: Concrete structure (RCC) 74%Jun 2025: Concrete structure (RCC) 74%Dec 2025: Concrete structure (RCC) 74%Jul 2026: Concrete structure (RCC) 74%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 4%Jun 2025: Final finishes 4%Dec 2025: Final finishes 4%Jul 2026: Final finishes 4%Excavation 100%Concrete structure (RCC) 74%Final finishes 4%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%74%4%315
100%74%4%279
100%74%4%265
100%24%0%184
97%0%0%114

"—" means MahaRERA shows no figure for that update.

About this project

Kalpataru Jade Skyline (MahaRERA P52100033791) is a residential project by Astrum Developments Private Limited in Baner, Pune 411045. It was launched in March 2022. It has 465 units in 1 building, with 1 RK, 1 BHK, 2 BHK, 3 BHK & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 74% complete, final finishes 4% complete. MahaRERA records do not show it as ready to move in.

315 of its 465 units are booked (68%). Since the December 2025 update, 36 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹14,800 per sq ft or less (up 2% on 2025), counting balconies and terrace in the size, based on 46 registered sales. Buyers here paid a rate about 20% higher than at other Baner projects in 2026. Most buyers paid ₹1.64–1.80 crore for flats of 1,190 sq ft. Its studios (under 450 sq ft) sold at ₹16,200 per sq ft or less in 2026 (33 sales); studios are priced separately from flats.

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033791.Check it on MahaRERA (P52100033791)All projects in Baner, Balewadi, Mahalunge