The Balmoral Towers, Balewadi

by Kasturi Spaces Private Limited. Balewadi, Pune 411045. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2028 – Dec 2030varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
45%Mid-construction1 of 4 phases with structure completeWeighted across 4 phases
Units booked
153 of 27655% booked · 2 phases not reported
Price per sq ft
₹18,0002026 salesup 7% on 2025See what buyers paid

Project facts

2 BHK24
3 BHK245
4 BHK253
5+ BHK8
Total units576
Buildings4
Land5.4 acres
Phases4
Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
3 BHKabout 1,030 – 1,240 sq ft₹1.91 – 2.31 crore2026 sales

Price per sq ft, year by year

2024₹16,500 per sq ft
2025up 2% on 2024₹16,800 per sq ft
2026up 7% on 2025₹18,000 per sq ft

Registered sales across all 4 phases.

Compared with the typical Balewadi rate in 2026: about 20% higher

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
The Balmoral Towers - Tower C, Phase II
Mid-construction
P5210004700813840%76%
The Balmoral Towers - Tower D, Phase I
Mid-construction
P5210004700913832%35%
The Balmoral Towers - Tower B, Phase III
Early stage
P521000772581160%Not reported
The Balmoral Towers - Tower A, Phase IV
Nearing possession
PR1260002600483138100%Not reported
Show updates by phase

The Balmoral Towers - Tower C, Phase II (P52100047008)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%40%0%105
100%40%0%24

"—" means MahaRERA shows no figure for that update.

The Balmoral Towers - Tower D, Phase I (P52100047009)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%32%0%48
100%32%0%18

"—" means MahaRERA shows no figure for that update.

The Balmoral Towers - Tower B, Phase III (P52100077258)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%—

"—" means MahaRERA shows no figure for that update.

The Balmoral Towers - Tower A, Phase IV (PR1260002600483)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411045

Projects with 250–1,100 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 10 mths5 yrs 1 mth
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028 – Dec 2030March 2028
Concrete structure (RCC)45%58%
Units booked55%65%
MahaRERA complaints (filed by or against the builder)40

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

The Balmoral Towers is a project by Kasturi Spaces Private Limited in Balewadi, Pune 411045, registered with MahaRERA as 4 phases (P52100047008, P52100047009, P52100077258, PR1260002600483). The first phase was launched in September 2022. Together the phases have 576 units in 4 buildings, with 2, 3, 4 & 5+ BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from December 2028 to December 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 45% complete and final finishes 0% complete. 1 of the 4 phases have their structure complete.

153 of the 276 units reported for sale are booked (55%); 2 phases have not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹18,000 per sq ft or less (up 7% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 20% higher than the typical Balewadi rate in 2026. Most buyers paid ₹1.91–2.31 crore for 3 BHK flats of about 1,030–1,240 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100047008, P52100047009, P52100077258 and PR1260002600483.Open MahaRERA and search P52100047008All projects in Baner, Balewadi, Mahalunge