27 Grand Residences, Balewadi

by Majestique Luxury Homes LLP. Balewadi, Pune 411045. View on Google Maps

Launched
First of 2 phases
Possession dates (MahaRERA)
Dec 2027No phase has an extended possession date
Concrete structure (RCC)
95%Mid-construction1 of 2 phases with structure completeWeighted across 2 phases
Units booked
211 of 27178% booked
Price per sq ft
₹14,8002026 salesup 3% on 2025See what buyers paid

Project facts

2 BHK128
3 BHK128
Total units271
Buildings2
Land0.7 acres
Phases2

Since Dec 2025: booked 164 → 211

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 790 sq ft₹76 lakh – ₹1.19 crore2026 sales
3 BHKabout 1,190 sq ft₹1.35 – 1.72 crore2025 sales

Price per sq ft, year by year

2023₹12,100 per sq ft
2024up 20% on 2023₹14,500 per sq ft
2025down 1% on 2024₹14,400 per sq ft
2026up 3% on 2025₹14,800 per sq ft

Registered sales across all 2 phases.

Compared with the typical Balewadi rate in 2026: about 5% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
27 Grand Residences- Tower 1
Nearing possession
P52100046445128100%87%
27 Grand Residences- Tower 2
Mid-construction
P5210004731412890%68%
Show updates by phase

27 Grand Residences- Tower 1 (P52100046445)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%124
100%75%0%102
100%50%0%102
100%3%0%102
100%0%0%88

"—" means MahaRERA shows no figure for that update.

27 Grand Residences- Tower 2 (P52100047314)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%87
100%50%0%62
100%10%0%62
100%0%0%62
100%0%0%47

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411045

Projects with 100–600 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411045
MeasureThis projectSimilar projects
Promised timeline (launch to possession)5 yrs 4 mths5 yrs 4 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)Dec 2027September 2028
Concrete structure (RCC)95%45%
Units booked78%61%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

27 Grand Residences is a project by Majestique Luxury Homes LLP in Balewadi, Pune 411045, registered with MahaRERA as 2 phases (P52100046445, P52100047314). The first phase was launched in July 2022. Together the phases have 271 units in 2 buildings, with 2 & 3 BHK homes as registered with MahaRERA. All 2 phases are active on MahaRERA.

The registered possession date is December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 95% complete and final finishes 15% complete. 1 of the 2 phases have their structure complete.

211 of the 271 units reported for sale are booked (78%). In 2026 registered sales, 80% of flats here sold at ₹14,800 per sq ft or less (up 3% on 2025), counting balconies and terrace in the size. Buyers here paid a rate about 5% lower than the typical Balewadi rate in 2026. Most buyers paid ₹76 lakh–₹1.19 crore for 2 BHK flats of about 790 sq ft (2026 sales); ₹1.35–1.72 crore for 3 BHK flats of about 1,190 sq ft (2025 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Majestique's track record in Pune

MahaRERA projects registered 2017–2026 in Pune & PCMC

Projects registered with MahaRERA74
Completed without extending the possession date35
Completed after an extension0
Lapsed9
Under construction30
Possession date extended on the builder's application1
Typical time from launch to 100% structure3 years 8 months
MahaRERA complaints (filed by or against the builder), all Majestique projects30 (11 of 74 projects)

See all Majestique projects →

Source: MahaRERA registrations P52100046445 and P52100047314.Open MahaRERA and search P52100046445All projects in Baner, Balewadi, Mahalunge