VTP Bellissimo Phase 1, Hinjewadi

by Magnite Developers Private Limited. Hinjewadi, Pune 411057. View on Google Maps

Launched
4 years originally promised
Possession date (MahaRERA)
2 months awayExtended by 9 months (originally March 2026). Why possession dates change
Concrete structure (RCC)
85%Mid-constructionAverage across 7 buildings
Units booked
1,191 of 1,24696% booked
Price per sq ft (incl. balconies and terrace)
₹11,6002026 so far · 17 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

1 BHK205
2 BHK719
3 BHK302
Other units (shops, offices or not given by type)20
Total units1,246
Buildings7
Land1.1 acres
Complaints on MahaRERA (filed by or against the builder)14

Since Dec 2025: booked 1,178 → 1,191 · structure 29% → 85% · complaints 6 → 14

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
730 – 800 sq ft₹80 – 83 lakh

Based on flats sold in 2024.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹10,500 per sq ft13 sales
2026 so far₹11,600 per sq ft17 sales

Rate vs other Hinjewadi projects, 2026: about 5% lower

Compared with 3 similar projects in PIN 411057

Projects with 600–2,500 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 411057
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs4 yrs 2 mths
Possession date extendedBy 9 months0 of 3
Possession date (MahaRERA)December 2026December 2026
Concrete structure (RCC) complete85%100%
Share of units booked96%93%
Complaints on MahaRERA (filed by or against the builder)141

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
All of the originally promised 4 years have passed
Concrete structure (RCC) 85% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 100%Jun 2024: Excavation 100%Dec 2024: Excavation 100%Jun 2025: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 3%Jun 2024: Concrete structure (RCC) 20%Dec 2024: Concrete structure (RCC) 29%Jun 2025: Concrete structure (RCC) 29%Dec 2025: Concrete structure (RCC) 29%Jul 2026: Concrete structure (RCC) 85%Dec 2023: Final finishes 0%Jun 2024: Final finishes 0%Dec 2024: Final finishes 0%Jun 2025: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 85%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%0%1,191
100%29%0%1,178
100%29%0%1,193
100%20%0%1,193
100%3%0%451

"—" means MahaRERA shows no figure for that update.

Other phases of this project

About this project

VTP Bellissimo Phase 1 (MahaRERA P52100033888) is a residential project by Magnite Developers Private Limited in Hinjewadi, Pune 411057. It was launched in March 2022. It has 1,246 units in 7 buildings: 1,226 homes (1, 2 & 3 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 9 months from the original March 2026. Construction, averaged across its 7 buildings: excavation complete, structure (RCC) 85% complete, final finishes not started. MahaRERA records do not show it as ready to move in.

1,191 of its 1,246 units are booked (96%). Since the December 2025 update, 13 more units have been booked and the reported concrete structure (RCC) has gone from 29% to 85%. 80% of the 2026 (so far) sales we found here were at ₹11,600 per sq ft or less, counting balconies and terrace in the size, based on 17 registered sales. Buyers here paid a rate about 5% lower than at other Hinjewadi projects in 2026. Most buyers paid ₹80–83 lakh for flats of 730–800 sq ft.

VTP's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA70
Completed without extending the possession date26
Completed after an extension, or lapsed13
Under construction31
Possession date extended by the builder10
Typical time from launch to 100% structure4 years 11 months
Complaints on MahaRERA, all VTP projects656 (60 of 70 projects)

See all VTP projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100033888.Check it on MahaRERA (P52100033888)All projects in Wakad, Hinjewadi, Marunji