Sukhwani Sepia, 97 Sepia, Phase III, Tathawade

by Ghanshyam Jhangaldas Sukhwani. Tathawade, Pune 411033. View on Google Maps

Launched
4 years 9 months promised
Possession date (MahaRERA)
1 year 2 months awayPossession date unchanged since launch
Concrete structure (RCC)
36%Mid-constructionAverage across 4 buildings
Units booked
141 of 39436% booked
Price per sq ft (incl. balconies and terrace)
₹10,1002026 so far · 12 sales80% of the 2026 sales we found were at this rate or lessSee what buyers paid

Project facts

2 BHK219
3 BHK175
Total units394
Buildings4
Land3.3 acres
Complaints on MahaRERA (filed by or against the builder)0

Since Dec 2025: booked 18 → 141 · total units 66 → 394

Share on WhatsApp

What buyers paid here

From government sale records

The price per sq ft is the agreed price of the flat alone, counting balconies and terrace.

Flat sizes and prices

Flat sizeWhat most buyers paid
760 – 810 sq ft₹69 – 78 lakh

Based on flats sold in 2026 so far.

Price per sq ft, year by year

80% of the flats sold in each year went for this price or less.

2024₹9,700 per sq ft29 sales
2026 so far₹10,100 per sq ft12 sales

Rate vs other Tathawade projects, 2026: similar

Compared with 6 similar projects in PIN 411033

Projects with 150–800 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 9 mths3 yrs 8 mths
Possession date extendedNo2 of 6
Possession date (MahaRERA)December 2027June 2027
Concrete structure (RCC) complete36%100%
Share of units booked36%89%
Complaints on MahaRERA (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

Construction progress

As reported to MahaRERA at each update
Time used and structure built
3 years 7 months of the promised 4 years 9 months have passed
Concrete structure (RCC) 36% complete
Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2023Jun 2024Dec 2024Jun 2025Dec 2025Jul 2026Dec 2023: Excavation 88%Jun 2024: Excavation 94%Dec 2024: Excavation 99%Jun 2025: Excavation 99%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2023: Concrete structure (RCC) 2%Jun 2024: Concrete structure (RCC) 9%Dec 2024: Concrete structure (RCC) 24%Jun 2025: Concrete structure (RCC) 24%Dec 2025: Concrete structure (RCC) 36%Jul 2026: Concrete structure (RCC) 36%Dec 2023: Final finishes 17%Jun 2024: Final finishes 17%Dec 2024: Final finishes 17%Jun 2025: Final finishes 17%Dec 2025: Final finishes 17%Jul 2026: Final finishes 17%Excavation 100%Concrete structure (RCC) 36%Final finishes 17%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%36%17%141
100%36%17%18
99%24%17%110
94%9%17%98
88%2%17%23

"—" means MahaRERA shows no figure for that update.

About this project

Sukhwani Sepia, 97 Sepia, Phase III (MahaRERA P52100050089) is a residential project by Ghanshyam Jhangaldas Sukhwani in Tathawade, Pune 411033. It was launched in March 2023. It has 394 units in 4 buildings, with 2 & 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction, averaged across its 4 buildings: excavation complete, structure (RCC) 36% complete, final finishes 17% complete. MahaRERA records do not show it as ready to move in.

141 of its 394 units are booked (36%). Since the December 2025 update, 123 more units have been booked. 80% of the 2026 (so far) sales we found here were at ₹10,100 per sq ft or less, counting balconies and terrace in the size, based on 12 registered sales. Buyers here paid a rate similar to other Tathawade projects in 2026. Most buyers paid ₹69–78 lakh for flats of 760–810 sq ft.

Sukhwani's track record in Pune

MahaRERA projects registered 2017–2026, in the 59 areas FlatNama covers

Projects registered with MahaRERA28
Completed without extending the possession date14
Completed after an extension, or lapsed3
Under construction11
Possession date extended by the builder4
Complaints on MahaRERA, all Sukhwani projects10 (4 of 28 projects)

See all Sukhwani projects →

Disclaimers
  • Figures are as reported to MahaRERA, not verified by FlatNama.
  • Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
  • On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
  • Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
  • Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
  • Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
  • Rates also vary with the exact project location.
  • Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
  • Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
  • Please do your own checks before you buy.
Source: MahaRERA registration P52100050089.Check it on MahaRERA (P52100050089)All projects in Tathawade, Punawale, Jambhe