7 Plumeria Drive- Phase 3, Punawale
by B A Consulting. Punawale, Pune 411033. View on Google Maps
- Launched
- 3 years originally promised
- Possession date (MahaRERA)
- 1 month agoExtended by 6 months (originally March 2026). Why possession dates change
- Concrete structure (RCC)
- 100%Nearing possessionAverage across 3 buildings
- Units booked
- 177 of 27564% booked
Project facts
| 1 BHK | 29 |
|---|---|
| 2 BHK | 5 |
| 3 BHK | 179 |
| 4 BHK | 62 |
| Total units | 275 |
| Buildings | 3 |
| Land | 4.5 acres |
| Complaints on MahaRERA (filed by or against the builder) | 0 |
Since Dec 2025: booked 153 → 177 · structure 0% → 100% · final finishes 0% → 59% · possession date March 2026 → September 2026
Compared with 6 similar projects in PIN 411033
Projects with 100–600 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Promised timeline (launch to possession) | 3 yrs | 4 yrs 8 mths |
| Possession date extended | By 6 months | 1 of 6 |
| Possession date (MahaRERA) | September 2026 | December 2027 |
| Concrete structure (RCC) complete | 100% | 92% |
| Share of units booked | 64% | 70% |
| Complaints on MahaRERA (filed by or against the builder) | 0 | 0 |
"Similar projects" shows the typical (middle) value. Other phases of this project are not included.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| VIVANTA Next | March 2023 | September 2026 | 100% | 249 of 285 booked (87%) |
| Anika Piccadilly Phase 2 | March 2023 | December 2027 | 100% | 229 of 244 booked (94%) |
| Merlin Elementa 2.0 | March 2023 | December 2027 | 83% | 242 of 406 booked (60%) |
| Sukhwani Sepia, 97 Sepia, Phase III | March 2023 | December 2027 | 36% | 141 of 394 booked (36%) |
| Aishwaryam Future | January 2023 | October 2027 | 40% | 159 of 308 booked (52%) |
| K Shire Phase 2 | May 2023 | December 2027 | 100% | 317 of 397 booked (80%) |
Construction progress
As reported to MahaRERA at each updateUpdates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 59% | 177 | |
| 17% | 0% | 0% | 153 | |
| 17% | 0% | 0% | — |
"—" means MahaRERA shows no figure for that update.
Other phases of this project
About this project
7 Plumeria Drive- Phase 3 (MahaRERA P52100050087) is a residential project by B A Consulting in Punawale, Pune 411033. It was launched in March 2023. It has 275 units in 3 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2026, extended by 6 months from the original March 2026. Construction, averaged across its 3 buildings: excavation complete, structure (RCC) complete, final finishes 59% complete. MahaRERA records do not show it as ready to move in.
177 of its 275 units are booked (64%). Since the December 2025 update, 24 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from March 2026 to September 2026.
Disclaimers
- Figures are as reported to MahaRERA, not verified by FlatNama.
- Concrete structure (RCC) is the reinforced-concrete frame. Final finishes means lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
- On MahaRERA, Lapsed means the registered possession date has passed and the developer has not filed an extension or recorded the project as complete. It does not by itself mean work has stopped.
- Total internal area = carpet + balcony + terrace, as Pune sales offices quote “carpet area”. Price per sq ft counts balconies and terrace in the size.
- Prices are of the flat alone; stamp duty, registration and GST are extra, so the total is usually 10–15% more.
- Prices in a project usually rise as construction progresses. Floor, view and flat size move the price up or down, so treat these figures as a guide.
- Rates also vary with the exact project location.
- Prices come from sale records obtained from IGR Maharashtra, which may not include every sale.
- Complaints are the count MahaRERA shows for the project; they include complaints filed by the builder against buyers.
- Please do your own checks before you buy.