Basil Maximus, Punawale

by Basil Avante LLP. Punawale, Pune 411033. View on Google Maps

Launched
First of 4 phases
Possession dates (MahaRERA)
Dec 2027 – Dec 2029varies by phaseNo phase has an extended possession date
Concrete structure (RCC)
40%Mid-construction1 of 4 phases with structure completeWeighted across 4 phases
Units booked
455 of 60675% booked · 1 phase not reported
Price per sq ft
₹9,5002026 salesabout the same as 2025See what buyers paid

Project facts

1 BHK5
2 BHK348
3 BHK331
4 BHK3
Total units755
Buildings5
Land6.4 acres
Phases4

Since Dec 2025: booked 428 → 455

Share on WhatsApp

Shortlist 2 or more to compare side by side.

What buyers paid here

From government sale records

What buyers paid in registered sales, not today's asking price. Use it to compare projects, then ask the builder for the current rate.

Flat types, sizes and prices

Flat typeSize (total internal area)What most buyers paidYear
2 BHKabout 790 sq ft₹73 – 76 lakh2026 sales
3 BHKabout 1,170 sq ft₹1.05 – 1.10 crore2026 sales

Price per sq ft, year by year

2023₹8,400 per sq ft
2024up 5% on 2023₹8,800 per sq ft
2025up 8% on 2024₹9,500 per sq ft
2026about the same as 2025₹9,500 per sq ft

Registered sales across all 4 phases.

Compared with the typical Punawale rate in 2026: about 10% lower

How to read this price
  • 80% of registered sales that year were at this rate or less.
  • Size is total internal area: carpet + balcony + terrace.
  • Higher floors, corner flats and open views usually cost more; lower floors and road-facing flats often less.
  • The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.
  • Fewer sales means a less certain figure.
  • Use it as a starting point for questions, not as an offer price.

Why this rate differs from other websites

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Basil Maximus Wing D and E
Nearing possession
P52100051323240100%96%
Basil Maximus Wing F
Mid-construction
P5210005635614915%69%
Basil Maximus Wing G
Mid-construction
P5210008009214910%38%
Basil Maximus Wing H
Early stage
PR12600025030191490%Not reported
Show updates by phase

Basil Maximus Wing D and E (P52100051323)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%294
100%98%0%289
100%35%0%258
100%20%0%24
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Basil Maximus Wing F (P52100056356)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%105
70%0%0%97
0%0%0%88
0%0%0%11

"—" means MahaRERA shows no figure for that update.

Basil Maximus Wing G (P52100080092)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%56
100%15%0%42
0%0%0%—

"—" means MahaRERA shows no figure for that update.

Basil Maximus Wing H (PR1260002503019)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%—

"—" means MahaRERA shows no figure for that update.

Compared with 6 similar projects in PIN 411033

Projects with 300–1,400 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 411033
MeasureThis projectSimilar projects
Promised timeline (launch to possession)4 yrs 6 mths4 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2027 – Dec 2029March 2028
Concrete structure (RCC)40%92%
Units booked75%75%
MahaRERA complaints (filed by or against the builder)00

"Similar projects" shows the typical (middle) value. Other phases of this project are not included.

How to read construction stages
Early stage
The concrete structure (RCC) has not started yet.
Mid-construction
The concrete structure (RCC) is being built.
Nearing possession
The concrete structure (RCC) is complete and final finishes are below 90%.
Ready to move
MahaRERA shows the project Completed, or the concrete structure (RCC) is complete and final finishes are 90% or more.
Concrete structure (RCC)
The reinforced-concrete frame of the building: columns, beams and slabs.
Final finishes
Lifts, services, common areas and other works needed before handover, not the finishes inside each flat.
Lapsed
MahaRERA status when the possession date has passed with no extension or completion filed; it does not by itself mean work has stopped.

How to read construction stages

About this project

Basil Maximus is a project by Basil Avante LLP in Punawale, Pune 411033, registered with MahaRERA as 4 phases (P52100051323, P52100056356, P52100080092, PR1260002503019). The first phase was launched in June 2023. Together the phases have 755 units in 5 buildings, with 1, 2, 3 & 4 BHK homes as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 40% complete and final finishes 0% complete. 1 of the 4 phases have their structure complete.

455 of the 606 units reported for sale are booked (75%); 1 phase has not reported bookings. In 2026 registered sales, 80% of flats here sold at ₹9,500 per sq ft or less (about the same as 2025), counting balconies and terrace in the size. Buyers here paid a rate about 10% lower than the typical Punawale rate in 2026. Most buyers paid ₹73–76 lakh for 2 BHK flats of about 790 sq ft (2026 sales); ₹1.05–1.10 crore for 3 BHK flats of about 1,170 sq ft (2026 sales). The registered price includes parking and floor-rise; GST, stamp duty and registration are extra.

Source: MahaRERA registrations P52100051323, P52100056356, P52100080092 and PR1260002503019.Open MahaRERA and search P52100051323All projects in Tathawade, Punawale, Jambhe